TITLE 20. PUBLIC UTILITIES AND TELECOMMUNICATIONS
STATE CORPORATION COMMISSION
Reproposed Regulation
REGISTRAR'S NOTICE: The State Corporation Commission is exempt from the Administrative Process Act in accordance with § 2.2-4002 A 2 of the Code of Virginia, which exempts courts, any agency of the Supreme Court, and any agency that by the Constitution is expressly granted any of the powers of a court of record.
Title of Regulation: 20VAC5-314. Regulations Governing Interconnection of Small Electrical Generators (adding 20VAC5-314-10 through 20VAC5-314-170).
Statutory Authority: §§ 12.1-13 and 56-578 of the Code of Virginia.
Public Hearing Information: Public hearing will be held upon request.
Public Comments: Public comments may be submitted until 5 p.m. on January 15, 2009.
Agency Contact: Michael Martin, Senior Utilities Engineer, State Corporation Commission, P.O. Box 1197, Richmond, VA 23218, telephone (804) 371-9336, FAX (804) 371-9350, or email mike.martin@scc.virginia.gov.
Summary:
Pursuant to § 56-578 A of the Virginia Electric Utility Restructuring Act, Chapter 23 (§ 56 576 et seq.) of Title 56 of the Code of Virginia (Restructuring Act), all electric energy distributors have the obligation to connect any retail customer, including those using distributed generation, located within its service territory to the distributor's facilities used for delivery of retail electric energy, subject to State Corporation Commission (commission) rules and regulations and approved tariff provisions relating to connection of service. In accordance with § 56-578 C of the Restructuring Act, the commission proposed interconnection standards, not inconsistent with nationally recognized standards, to ensure transmission and distribution safety and reliability. Based upon comments received on the proposed interconnection standards published in the Virginia Register, the commission now directs that revisions to the proposed interconnection standards be made available for comment. These interconnection standards are now republished as reproposed regulations for further comment.
The interconnection regulations establish standardized interconnection and operating requirements for the safe operation of electric generating facilities with a rated capacity of 20 MW or less connected to the distribution systems of electric utilities under the jurisdiction of the Virginia State Corporation Commission. These requirements apply to retail electric customers, independently owned generators or any other parties operating or intending to operate a distributed generation facility. The regulations establish three interconnection review paths for interconnection of customer-sited generation in Virginia - Level 1, Level 2 and Level 3. Level 1 interconnections must include a request to interconnect a certified inverter-based generating facility no larger than 500 kW. To qualify for a Level 2 interconnection request, the generating facility can be no larger than 2 MW and the proposed generator must meet certain specified codes, standards, and certification requirements. Level 3 interconnection requests apply to generating facilities larger than 2 MW but no larger than 20 MW or a generating facility that does not pass the Level 1 or Level 2 Process. The revised proposed interconnection regulations for distributed generation are intended to more clearly delineate the responsibility of each party under an interconnection agreement. The revisions also clearly identify the cost responsibility of each party while more clearly identifying what costs can be charged interconnection customers. Moreover, the revisions are intended to make the interconnection regulations more readable.
AT RICHMOND, NOVEMBER 26, 2008
COMMONWEALTH OF VIRGINIA, ex rel.
STATE CORPORATION COMMISSION
CASE NO. PUE-2008-00004
Ex Parte: In the matter of establishing
interconnection standards for distributed
electric generation
ORDER
On February 26, 2008, the State Corporation Commission ("Commission") issued an Order Establishing Proceeding in the above-captioned case to consider interconnection standards for distributed generation for the Commonwealth in accordance with § 56‑578 A of the Virginia Electric Utility Restructuring Act, Chapter 23 (§ 56‑576 et seq.) of Title 56 of the Code of Virginia ("Code"). The Staff of the Commission developed proposed rules to meet the requirement of § 56‑578 C of the Restructuring Act, Chapter 314, Regulations Governing Interconnection of Small Electrical Generators, and the Commission directed that notice be given to the public and invited comments on Staff's proposed rules.
Following comments filed on Staff's proposed rules,1 the Commission granted Staff leave to file a response to the comments filed.2
On October 27, 2008, the Staff of the Commission filed its Motion for Leave to File ("Motion") requesting that it be granted leave to file its Staff Report, also filed on October 27, 2008, one business day out of time. The Staff Report includes revised rules in response to the comments filed.
NOW THE COMMISSION, having considered Staff's Motion, is of the opinion and finds that it should be granted. We further find that notice of Staff's revised rules, attached hereto as Appendix A, should be given to the public and that interested persons should have an opportunity to comment on Staff's revised rules (Appendix A).
Accordingly, IT IS ORDERED THAT:
(1) Staff is hereby granted its Motion and the Staff Report filed on October 27, 2008, is hereby received into the record of this case.
(2) The Commission's Division of Information Resources shall forward a copy of this Order including Appendix A to the Registrar of Regulations for publication in the Virginia Register.
(3) On or before January 15, 2009, interested persons may file an original and fifteen (15) copies of comments with Joel H. Peck, Clerk, State Corporation Commission, c/o Document Control Center, P.O. Box 2118, Richmond, Virginia 23218. Comments shall refer to Case No. PUE‑2008‑00004 and address Staff's revised rules (Appendix A).
(4) This matter shall remain open for further order of the Commission.
Commissioner Dimitri did not participate in this matter.
AN ATTESTED COPY hereof shall be sent by the Clerk of the Commission to: T. Borden Ellis, Senior Attorney, Legal, NiSource Corporate Services Company, 1809 Coyote Drive, Chester, Virginia 23836; Noelle J. Coates, Esquire, Hunton & Williams LLP, Riverfront Plaza, East Tower, 951 East Byrd Street, Richmond, Virginia 23219-4074; Horace P. Payne, Jr., Esquire, Dominion Resources Services, Inc., 120 Tredegar Street, RS‑2, Richmond, Virginia 23219; John A. Pirko, Esquire, LeClairRyan, P.C., 4201 Dominion Boulevard, Suite 200, Glen Allen, Virginia 23060; Charles E. Bayless, Esquire, Appalachian Power Company, P.O. Box 1986, Charleston, West Virginia 25327; Kevin Fox, Esquire, Keyes & Fox LLP, 5727 Keith Avenue, Oakland, California 94618; C. Meade Browder, Jr., Senior Assistant Attorney General, Division of Consumer Counsel, Office of Attorney General, 900 East Main Street, 2nd Floor, Richmond, Virginia 23219; and the Commission's Office of General Counsel and Divisions of Energy Regulation and Economics and Finance.
_______________________________________
1 The Commission granted extensions for comments to be filed on May 15, 2008, and August 28, 2008.
2 Order issued August 28, 2008. The Staff was granted a filing extension to October 24, 2008, by Order Granting Extension to Staff issued September 24, 2008.
CHAPTER 314
REGULATIONS GOVERNING INTERCONNECTION OF SMALL ELECTRICAL GENERATORS
20VAC5-314-10. Applicability and scope.
These regulations are promulgated pursuant to
§ 56-578 of the Virginia Electric Utility Restructuring Act (§ 56-576
et seq. of the Code of Virginia). They establish standardized interconnection
and operating requirements for the safe operation of electric generating
facilities with a rated capacity of 20 megawatts (MW) or less connected to
[ distribution companies' electric utility ] distribution
[ (and in certain cases transmission) ] systems in
Virginia. These [ requirements regulations ]
apply to retail electric customers, independently owned generators
[ or and ] any other parties operating
[ , ] or intending to operate [ , ]
a distributed generation facility [ in parallel with a utility's
system and to the utility ]. [ Interconnections
These regulations do not apply to customer generators operating pursuant to the
commission's Regulations Governing Net Energy Metering (20VAC5-315) or those ]
that fall under the jurisdiction of the Federal Energy Regulatory Commission
[ are not subject to these regulations ].
[ If the utility has turned over control of its transmission system to a Regional Transmission Entity (RTE), and if the small generator interconnection process identifies upgrades to the transmission system as necessary to interconnect the small generating facility, then the utility will coordinate with the RTE, and the procedures herein will be adjusted as necessary to satisfy the RTE's requirements with respect to such upgrades. ]
There are three [ interconnection ]
review paths for [ the ] interconnection of
[ customer-sited ] generation in Virginia
[ having an output of not more than 20 MW ]:
Level 1 - A request to interconnect a [ certified
inverter-based ] small generating facility [ (SGF) ]
no larger than 500 kilowatts (kW) shall be evaluated under the Level 1
process.
Level 2 - A request to interconnect a certified [ small
generating facility SGF no ] larger than [ 500
kW but no larger than ] 2 MW [ and not qualifying
for the Level 1 process ] shall be evaluated under the Level 2
process.
Level 3 - A request to interconnect [ a
small generating facility larger than 2 MW but an SGF ] no
larger than 20 MW [ or a small generating facility that does not
pass and not qualifying for ] the Level 1 [ process ]
or Level 2 process, shall be evaluated under the Level 3 process.
[ An SGF proposed to be interconnected to a distribution feeder may be limited to a capacity substantially less than 20 MW, depending upon the characteristics of that feeder and the potential for upgrading it, as well as the nature of the loads and other generation on the feeder relative to the proposed point of interconnection. ]
The utility shall designate an employee or office from
which [ the interconnection customer ("IC") may
informally request ] information [ on
concerning ] the application process [ can be
obtained through informal requests from the interconnection customer presenting
a proposed project for a specific site ]. The name, telephone
number, and email address of such contact employee or office shall be made
available on the utility's Internet web site. Electric system information
[ for specific locations, feeders, or small areas
relevant to the location of the proposed SGF ] shall be provided to
the [ interconnection customer IC ] upon
request and may include [ relevant system studies, ]
interconnection studies [ , ] and [ any ]
other [ relevant ] materials [ useful to
an understanding of an interconnection at a particular point on the utility's
system ], to the extent such provision does not violate
confidentiality provisions of prior agreements or [ release ]
critical infrastructure [ requirements information ].
The utility shall comply with reasonable requests for such information unless
the information is proprietary or confidential and cannot be provided pursuant
to a confidentiality agreement.
The utility shall make reasonable efforts to meet all time
frames provided in these [ procedures regulations ]
unless the utility and the [ interconnection customer
IC ] agree to a different schedule. If the utility cannot meet a
deadline provided herein, it shall notify the [ interconnection
customer IC ], explain the reason for the failure to
meet the deadline, and provide an estimated time by which it will complete the
applicable interconnection procedure in the process.
20VAC5-314-20. Definitions.
The following terms when used in this chapter shall have the following meaning unless the context clearly indicates otherwise:
"Affected system" means an electric [ utility ]
system other than [ that of ] the [ utility's
distribution system utility ] that may be affected by
the proposed interconnection.
[ "Affected system operator" means an entity that operates an affected system or, if the affected system is under the operational control of an independent system operator or a regional transmission entity, such independent entity.
"Applicable laws and regulations" means all duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any government authority.
"Attachment facilities" means the facilities and equipment owned, operated, and maintained by the utility that are built new in order to physically connect the customer's interconnection facilities to the utility system. Attachment facilities shall not include distribution upgrades or previously existing distribution and transmission facilities. ]
"Business day" means Monday through Friday, excluding federal holidays.
[ "Certified" has the meaning ascribed to it in Schedule 2 of this chapter.
"Customer's interconnection facilities" means all of the facilities and equipment owned, operated and maintained by the interconnection customer, between the small generating facility and the point of interconnection necessary to physically and electrically interconnect the small generating facility to the utility system. ]
"Commission" means the Virginia State Corporation Commission.
[ "Distribution company" means the
utility that owns and/or operates the distribution system located in Virginia
to which the small generation facility proposes to interconnect its small
generating facility. ]
[ "Default" means the failure of a breaching party to cure its breach under the small generator interconnection agreement. ]
"Distribution system" means [ a
the ] utility's facilities and equipment generally delivering
electricity to ultimate customers from substations supplied by higher voltages
(usually at transmission level). For purposes of these [ interconnection
rules regulations], all portions of the [ distribution
company's utility's ] transmission system regulated by
the commission for which interconnections are not within Federal Energy
Regulatory Commission (FERC) jurisdiction are considered [ also ]
to be [ part of subject to ] these
interconnection [ rules regulations ].
"Distribution upgrades" means the additions,
modifications, and upgrades to the utility's distribution system at or beyond
the point of interconnection [ to facilitate
necessary to abate problems on the utility's distribution system caused by the ]
interconnection of the small generating facility [ and to
render the service necessary to effect the interconnection customer's operation
of on-site generation ]. Distribution upgrades do not include
[ customer's ] interconnection facilities [ or
attachment facilities ].
"Energy service provider" means any entity
supplying electric energy [ service ] to the
[ producer, either as tariffed, competitive, or default service
pursuant to § 56-585 of the Code of Virginia interconnection
customer ].
[ "Facilities study" has the meaning ascribed to it in 20VAC5-314-70 E.
"Feasibility study" has the meaning ascribed to it in 20VAC5-314-70 C.
"FERC" means the Federal Energy Regulatory Commission.
"Good Utility Practice" means any of the practices, methods and acts engaged in or approved by a significant portion of the electric industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good Utility Practice is not intended to be limited to the optimum practice, method, or act to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region.
"Governmental authority" means any federal, state, local or other governmental regulatory or administrative agency, court, commission, department, board, or other governmental subdivision, legislature, rulemaking board, tribunal, or other governmental authority having jurisdiction over the parties, their respective facilities, or the respective services they provide, and exercising or entitled to exercise any administrative, executive, police, or taxing authority or power; provided that such term does not include the interconnection customer, the utility or a utility affiliate. ]
"Interconnection customer" or "IC"
means any entity [ , including the utility, any affiliates or
subsidiaries of either, ] proposing to interconnect a new small
generating facility with the [ utility's utility ]
system [ under this chapter ] .
[ "Interconnection facilities" means the
utility's interconnection facilities and the interconnection customer's
interconnection facilities. Collectively, interconnection facilities include
all facilities and equipment between the small generating facility and the
point of interconnection, including any modification, additions or upgrades
that are necessary to physically and electrically interconnect the small
generating facility to the utility's distribution system. Interconnection
facilities are sole use facilities and shall not include distribution upgrades. ]
"Interconnection request" means the [ interconnection
customer's IC's ] request, in accordance with the
tariff, to interconnect a new small generating facility, or to increase the
capacity of, or make a material modification to the operating characteristics
of, an existing small generating facility that is interconnected with the
[ utility's utility ] system.
"Interconnection [ study
studies ] " means the [ study that is
undertaken studies conducted ] by the [ company
utility ], or a [ mutually agreed upon ]
third party agreed to by the [ company utility ]
and the [ producer interconnection customer ],
in order to determine the interaction of the small generating facility
[ and with ] the [ distribution
utility ] system [ , ] and
[ the affected systems in order ] to specify any
[ modification modifications ] to the small
generating facility or the [ distribution system needed
electric systems studied ] to ensure safe and reliable operation of
the small generating facility in parallel with the [ distribution
utility ] system.
[ "Material modification" means a modification that has a material impact on the cost or timing of any interconnection request with a later queue priority date.
"Operating requirements" means any operating and technical requirements that may be applicable due to regional transmission entity, independent system operator, control area, or the utility's requirements, including those set forth in the Small Generator Interconnection Agreement. ]
"Party" or "parties" means the
utility, interconnection customer, or [ any combination thereof
both ].
"Point of interconnection" means the point where
the [ customer's ] interconnection facilities connect
[ with to ] the [ utility's
utility ] system.
[ "Producer" means a person operating a
small generating facility interconnected to the distribution system of a
utility for the purpose of parallel operation.
"Regional Transmission Entity" or "RTE" means an entity having the management and control of a utility's transmission system as further set forth in § 56-579 of the Code of Virginia. ]
"Small generating facility" [ or
"generator" or "SGF" ] means the
interconnection customer's [ device equipment ]
for the production of electricity identified in the interconnection request
[ , but shall not include the interconnection facilities not owned
by the interconnection customer ].
[ "Study process" means the procedure
for evaluating an interconnection request that includes the Level 3 scoping
meeting, feasibility study, system impact study, and facilities study.
"Small Generator Interconnection Agreement" or "SGIA" means the agreement between the utility and the interconnection customer as set forth in Schedule 6 of 20VAC5-314-170.
"Supplemental review" has the meaning ascribed to it in 20VAC5-314-60 G. ]
"System" [ or "utility system" ]
means the [ distribution and transmission ] facilities
owned, controlled, or operated by the utility that are used to [ provide
electric service under the tariff deliver electricity ].
[ "System impact study" has the meaning ascribed to in 20VAC5-314-70 E. ]
"Tariff" means the rates, terms and conditions filed by the utility with the commission for the purpose of providing commission-regulated electric service to retail customers.
[ "Transmission system" means the utility's facilities and equipment delivering electric energy to the distribution system, such facilities being operated at voltages above the utility's typical distribution system voltages. ]
"Utility" means the public utility company subject to regulation by the commission pursuant to Chapter 10 (§ 56-232 et seq.) of Title 56 of the Code of Virginia with regard to rates and/or service quality [ to which the interconnection customer proposes to interconnect a small generating facility ].
20VAC5-314-30. Siting of distributed generation facilities.
Prior to installing a small generating facility, the
[ IC interconnection customer ] must ensure
compliance with local, state and federal laws and regulations, including
[ siting. If the producer has satisfied the requirements of this
chapter and has submitted a copy of his interconnection notification form to
the commission's Division of Energy Regulation, the statutory requirements of §
56-580 D all applicable easements and permits, and §§ 56-265.2
and 56-580 ] of the Code of Virginia [ shall be deemed
to have been met, as applicable ].
20VAC5-314-40. Level 1 interconnection process.
[ A. ] The Level 1 interconnection
[ path process ] is available to any
[ IC interconnection customer ] proposing to
interconnect a small generating facility with the [ utility's
distribution utility ] system if the [ small
generating facility SGF ] is no larger than 500 kW.
[ In order to interconnect under this path, the small generating
facility shall complete the streamlined Interconnection Request Form
contained in 20VAC5-314-170 as Schedule 1. The utility shall follow the same
time line established by the commission in 20VAC5-315-30 of the Net Metering
Regulations.
B. An IC may begin operation of a small generating facility when:
1. The IC has completed the Level 1 Interconnection Request Form (Schedule 1 in 20VAC5-314-170) and submitted it to the utility with the required $100 processing fee attached. The utility shall submit a copy of the Interconnection Notification Form to the commission's Division of Energy Regulation. The utility may supply a commission-approved Interconnection Request Form similar to Schedule 1;
2. If required by the utility's tariff, the IC has installed a lockable, utility-accessible, load breaking manual disconnect switch;
3. A licensed electrician has certified, by signing the Interconnection Request Form, that any required manual disconnect switch has been installed properly and that the small generating facility has been installed in accordance with the manufacturer's specifications as well as all applicable provisions of the National Electrical Code;
4. The vendor of the SGF has certified on the Interconnection Request Form that the SGF equipment is in compliance with the requirements established by Underwriters Laboratories or other national testing laboratories in accordance with IEEE Standard 1547, Standard for Interconnecting Distributed Resources with Electric Power Systems;
5. In the case of a static inverter-connected SGF with an alternating current capacity in excess of 10 kilowatts, the IC has had the inverter settings inspected by the utility. The utility may not impose a charge for the inspection;
6. In the case of a nonstatic inverter-connected SGF, the IC has interconnected according to the utility's interconnection guidelines, and the utility has inspected all protective equipment settings. The utility may not impose a charge for such inspection.
7. In the case of an SGF having an alternating current capacity greater than 25 kilowatts, the following requirements shall be met before interconnection may occur:
a. Distribution facilities and customer impact limitations. An SGF shall not be permitted to interconnect to distribution facilities if the interconnection would reasonably lead to damage to any of the utility's facilities or would reasonably lead to voltage regulation or power quality problems at other customer revenue meters due to the incremental effect of the SGF on the performance of the system, unless the IC reimburses the utility for its cost to modify any facilities needed to accommodate the interconnection.
b. Secondary, service, and service entrance limitations. The capacity of the SGF shall be less than the capacity of the utility-owned secondary, service, and service entrance cable connected to the point of interconnection, unless the IC reimburses the utility for its cost to modify any facilities needed to accommodate the interconnection.
c. Transformer loading limitations. The SGF shall not have the ability to overload the utility's distribution transformer, or any distribution transformer winding, beyond manufacturer or nameplate ratings, unless the IC reimburses the utility for its cost to modify any facilities needed to accommodate the interconnection.
d. Integration with utility's grounding. The grounding scheme of the SGF shall comply with the IEEE 1547, Standard for Interconnecting Distributed Resources with Electric Power Systems, and shall be consistent with the grounding scheme used by the utility. If requested by an IC, the utility shall assist the IC in selecting a grounding scheme that coordinates with its distribution system.
e. Balance limitation. The SGF shall not create a voltage imbalance of more than 3.0% at any other customer's revenue meter if the utility distribution transformer, with the secondary connected to the point of interconnection, is a three-phase transformer, unless the IC reimburses the utility for its cost to modify any facilities needed to accommodate the interconnection.
C. Neither the utility nor the energy service provider shall impose any charges upon an IC for any interconnection requirements specified by this chapter, except as may be incurred in providing off-site metering.
D. The IC shall immediately notify the utility of any changes in the ownership of, operational responsibility for, or contact information for the SGF.
E. The utility shall not be required to maintain an interconnection with an SGF if the SGF or associated equipment is found to be out of compliance with the codes, standards and certifications applicable to the SGF. ]
20VAC5-314-50. Levels [ 1 2 ]
and [ 2 3 ] interconnection request
general requirements.
A. The interconnection customer shall submit [ it’s
a completed Levels 2 and 3 ] Interconnection Request Form
[ contained in (Schedule 4 of ] 20VAC5-314-170
[ (Schedule 4 ]) to the utility, with the processing
fee or deposit specified in the Interconnection Request Form. [ The
utility shall provide a copy of the Interconnection Request Form to the
commission's Division of Energy Regulation. ] The
Interconnection Request Form shall be date- and time-stamped upon receipt by
the utility [ , which. The date- and time-stamp of a
completed Interconnection Request Form ] shall be used as the
qualifying date- and time-stamp for the purposes of any timetable in these
procedures. The interconnection customer shall be notified of receipt by the
utility within three business days of receiving the interconnection request,
which notification may be [ to an by US mail, ]
email address or fax number provided by the IC.
The utility shall notify the interconnection customer
within 10 business days of the receipt of the Interconnection Request Form as
to whether the Interconnection Request Form is complete or incomplete. If the
Interconnection Request Form is incomplete, the utility shall [ provide,
along with the notice that the Interconnection Request Form is incomplete,
so notify the IC, including ] a written list detailing all
information that must be provided to complete the Interconnection Request Form.
The interconnection customer [ will
shall ] have 10 business days after receipt of the notice
[ of incomplete information ] to submit the listed
information or to request an extension of time to provide such information. If
the [ interconnection customer IC ] does
not provide the listed information or a request for an extension of time within
the deadline, the Interconnection Request Form will be deemed withdrawn.
[ An Interconnection Request Form will be deemed complete upon
submission of the listed information to the utility.
The utility shall provide a copy of the final completed date- and time-stamped Interconnection Request Form to the commission's Division of Energy Regulation. ]
B. Any [ material ] modification
to machine data or equipment configuration or to the interconnection site of
the small generating facility as specified in the Interconnection Request Form
but not agreed to in writing by the utility and the [ interconnection
customer IC ] may be deemed a withdrawal of the
Interconnection Request Form and may require submission of a new
Interconnection Request Form, unless proper notification of each party by the
other and a reasonable time to cure the problems created by the changes are
undertaken.
C. Site control documentation must be submitted with the
[ interconnection request Interconnection Request Form ].
[ Any information appearing in public records may not be labeled
Confidential. (Confidential information is discussed in 20VAC5-314-110.) ]
Site control may be demonstrated through:
1. Ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the small generating facility;
2. An option to purchase or acquire a leasehold site for such purpose;
3. An exclusivity or other business relationship between
the interconnection customer and the entity having the right to sell, lease, or
grant the [ interconnection customer IC ] the
right to possess or occupy a site for such purpose.
D. The utility shall place interconnection requests
[ in into ] a first come, first served
[ order per queue that is based on the interconnection's
distribution ] feeder and [ per
distribution ] substation [ . The queue position shall
be ] based upon the date- and time-stamp of the [ completed ]
Interconnection Request Form. The [ order of each
Interconnection Request Form queue position of an interconnection
request ] will be used to determine the cost responsibility for the
[ necessary ] upgrades [ necessary to
accommodate the interconnection ]. At the utility's option,
interconnection requests may be studied serially or in clusters for the purpose
of the system impact study.
[ E. The utility shall not be required to maintain an interconnection with an SGF if the SGF or associated equipment is found to be out of compliance with the codes, standards and certification applicable to the SGF. ]
20VAC5-314-60. Level 2 interconnection process.
A. The Level 2 interconnection process is available to an
interconnection customer proposing to interconnect a small generating facility
with the [ utility's distribution utility ] system
if the [ small generating facility SGF ] is
no larger than 2 MW and [ if the interconnection customer's
proposed small generating facility does not qualify for the Level 1
process, and ] meets the codes, standards, and certification
requirements of Schedules 2 and 3 in 20VAC5-314-170.
B. Within 15 business days after the utility notifies the
[ interconnection customer IC ] it has
received a complete [ interconnection request
Interconnection Request Form ], the utility shall perform an
initial review using the screens set forth below and shall notify the
[ interconnection customer IC ] of the
results including copies of the analysis and data underlying the utility's
determinations under the screens.
[ 1. The proposed small generating facility's point
of interconnection must be on a portion of the utility's distribution system
that is subject to the tariff. ]
[ C. Interconnection to radial circuits. ]
[2. 1. ] For interconnection of a
[ proposed ] small generating facility to a radial
distribution circuit, the aggregated generation, including the proposed small
generating facility, on the circuit shall not exceed 15% of the line section's
annual peak load as most recently measured at the substation or calculated for
the line [ segment section ]. A line
section is that portion of a [ utility's electric system
distribution circuit ] connected to a customer [ that
is ] bounded by automatic sectionalizing devices or the end of the
[ distribution line circuit ].
[ 3. 2. ] The [ proposed
small generating facility SGF ], in aggregation with
other generation on the distribution circuit, shall not contribute more than
10% to the [ distribution ] circuit's maximum
fault current at the point on the distribution [ feeder
feeder's (primary) ] voltage [ (primary) ]
level [ that is ] nearest the [ proposed ]
point of [ change of ownership interconnection ].
[ 4. 3. ] The [ proposed
small generating facility SGF ], in aggregate with other
generation on the distribution circuit, shall not cause any distribution
protective devices and equipment (including, but not limited to, substation
breakers, [ fuse fused ] cutouts, and
line reclosers), or interconnection customer equipment on the system to exceed
87.5% of the short circuit interrupting capability; nor shall the interconnection
be [ proposed for permitted on ] a
circuit [ that already exceeds where ] 87.5%
of the short circuit interrupting capability [ is already exceeded ].
[ 5. Using 4. For interconnections to
the distribution primary voltage, use ] the table below, [ to ]
determine the [ acceptable ] type of interconnection
to a primary distribution [ line circuit ].
This screen includes a review of the type of electrical service provided to the
[ interconnection customer IC ], including
line configuration and the transformer connection [ , ] to
limit the potential for creating over-voltages on the utility's [ electric
power distribution ] system due to a loss of ground
during the operating time of any anti-islanding function.
|
Primary Distribution Line Type |
Type of Interconnection to Primary Distribution Line |
Result/Criteria |
|
Three-phase, three wire |
Three-phase [ , ] or single phase, phase-to-phase |
Pass screen |
|
Three-phase, four wire |
Effectively-grounded three phase [ , ] or single-phase, line-to-neutral |
Pass screen |
[ 6. 5. ] If the [ proposed ]
small generating facility is to be interconnected [ on
to a ] single-phase shared secondary, the aggregate generation
capacity on the shared secondary, including the proposed [ small
generating facility SGF ], shall not exceed 20 kW.
[ 7. 6. ] If the [ proposed
small generating facility SGF ] is single-phase and is
to be interconnected on a center tap neutral of a 240 volt service, its
addition shall not create an imbalance between the two sides of the 240 volt
service of more than 20% of the nameplate rating of the service transformer.
[ 8. 7. ] The [ small
generating facility SGF ], in aggregate with [ other ]
generation interconnected to the transmission side of [ a
the ] substation transformer [ feeding
that feeds ] the [ distribution ] circuit
where the [ small generating facility SGF ] proposes
to interconnect [ , ] shall not exceed 10 MW in an area
where there are known, or posted, transient stability limitations to generating
units located in the general electrical vicinity (e.g., three or four
transmission busses from the point of interconnection).
[ 9. 8. ] No construction of
facilities by the utility on its own system shall be required to accommodate
the [ small generating facility SGF, except minor
modifications ].
[ C. D. ] Interconnections
to [ distribution systems secondary voltage networks
(120 volts to 480 volts) ].
1. For interconnection of a [ proposed ]
small generating facility to the load side of spot network protectors
serving more than a single customer, the [ proposed small
generating facility SGF ] must utilize an inverter-based
equipment package and, together with the aggregated other inverter-based
generation, shall not exceed the smaller of 5.0% of a spot network's maximum
load or 300 kW. For spot networks serving a single customer, the [ small
generating facility SGF ] must use [ an ]
inverter-based equipment package and either meet the requirements above
[ , ] or [ shall ] use a
protection scheme [ , ] or operate the generator so as
not to exceed on-site load or otherwise prevent nuisance operation of the spot
network protectors.
2. For interconnection of [ a proposed small
generating facility an SGF ] to the load side of area
network protectors, the [ proposed small generating facility
SGF ] must utilize an inverter-based equipment package and,
together with the aggregated other inverter-based generation, shall not exceed
the smaller of 10% of an area network's minimum load [ , ]
or 500 kW.
3. [ Notwithstanding subdivision 1 or 2 of
this subsection, each utility may incorporate into its interconnection
standards any change in interconnection guidelines related to networks pursuant
to standards developed under IEEE 1547 for interconnections to networks. ]
To the extent [ the any ] new IEEE
standards conflict with this chapter, [ in particular IEEE 1547, ]
the new standards shall apply. In addition, [ and with the
consent of the ] utility [ , a small generating
facility may be interconnected consent shall not be unreasonably
withheld from an SGF interconnecting ] to a spot or area network
provided the [ facility SGF ] utilizes a
protection scheme that will prevent any power export from the [ customer's
IC's ] site including inadvertent export under fault conditions
[ or, and ] otherwise prevent nuisance operation
of the network protectors.
[ D. E. ] If the
[ proposed ] interconnection passes the screens, the
interconnection request shall be approved and the utility will provide the
interconnection customer an executable interconnection agreement within
[ 10 five ] business days after the
determination.
[ E. F. ] If the
[ proposed ] interconnection fails any
screens, but the utility determines that the small generating facility may
nevertheless be interconnected consistent with safety, reliability, and power
quality standards, the utility shall provide the [ interconnection
customer IC ] an executable interconnection agreement
within five business days after the determination.
[ F. G. ] If the
[ proposed ] interconnection fails [ the
any ] screens, but the utility does not or cannot determine from
the initial review that the [ small generating facility
SGF ] may nevertheless be interconnected consistent with safety,
reliability, and power quality standards [ , ] unless
the [ interconnection customer IC ] is
willing to consider minor modifications or further study, the utility shall
provide the [ interconnection customer IC ] with
the opportunity to attend a customer options meeting.
[ G. H. ] If the utility
determines the [ Interconnection Request Form interconnection ]
cannot be approved without minor modifications at minimal cost; a
supplemental study or other additional studies or actions; or at significant
cost to address safety, reliability, or power quality problems, [ within
the five business day period after the determination, ] the
utility shall notify the [ interconnection customer
IC ] and provide copies of the data and analyses underlying its
conclusion [ within five business days after determination ].
Within 10 business days of the [ utility's ] determination,
the utility shall offer to convene a customer options meeting [ with
the utility ] to review possible [ interconnection
customer IC ] facility modifications [ , ]
or the screen analysis and related results, to determine what further steps
are needed to permit the [ small generating facility
SGF ] to be connected safely and reliably. At the time of
notification of the utility's determination, or at the customer options
meeting, the utility shall:
1. Offer to perform facility modifications or minor
modifications to the utility's electric system (e.g., changing meters, fuses,
relay settings) and provide [ a nonbinding good faith
an ] estimate of the [ limited ] cost
to make such modifications to the utility's electric system;
2. Offer to perform a supplemental review if the utility
concludes that the supplemental review might determine that the [ small
generating facility SGF ] could continue to qualify for
interconnection pursuant to the [ fast track Level 2 ]
process, and provide [ a nonbinding good faith an ]
estimate of the costs and time of such review; or
3. [ Obtain the interconnection customer's
agreement Offer ] to continue evaluating the
interconnection request [ , but ] under the Level 3
[ study interconnection ] process.
[ H. I. ] Supplemental
review.
If [ the interconnection customer agrees to ]
a supplemental review [ , is offered to ]
the interconnection customer [ shall agree in writing within
15 business days of the offer and submit a deposit for the estimated costs
provided in subdivision G 2 of this section and the IC agrees to the
supplemental review, the utility shall, within 10 business days of the request,
provide to the IC an appropriate supplemental review agreement. To maintain its
position in the utility’s interconnection queue, the IC must execute the
supplemental review agreement and return it to the utility, along with a
deposit for the estimated cost of the supplemental review, within 15 business
days after receipt of the agreement. If the IC fails to return the executed
supplemental review agreement along with the deposit within 15 business days
after receipt, the interconnection request shall be deemed withdrawn and shall
lose its place in the utility’s interconnection queue ].
The [ interconnection customer
IC ] shall be responsible for the utility's actual costs
[ for of ] conducting the supplemental
review. The [ interconnection customer IC ] shall
pay any review costs that exceed the deposit within [ 20
30 ] business days of receipt of the invoice or resolution of any
dispute. If the deposit exceeds the invoiced costs, the utility will return
such excess within [ 20 30 ] business
days of the invoice without interest.
Within 10 business days following receipt of the
[ supplemental review agreement and ] deposit [ for
a supplemental review ], the utility will determine if the
[ small generating facility SGF ] can
be interconnected safely and reliably.
1. If so, [ and if the supplemental review reveals that no modification are required to the customer’s interconnection facilities, or to the system, or to an affected system, ] the utility shall forward an executable interconnection agreement to the interconnection customer within five business days [ after the determination ].
2. If so, and [ interconnection customer facility
the customer’s interconnection facilities ] modifications are
required to allow the [ small generating facility SGF ]
to be interconnected consistent with safety, reliability, and power quality
standards under these procedures, the utility shall forward an executable
interconnection agreement to the [ interconnection customer
IC ] within five business days after confirmation that the
[ interconnection customer IC ] has agreed to
make the necessary changes at the [ interconnection customer's
IC’s ] cost.
3. If so, and minor modifications to the utility's electric
system are required to allow the [ small generating facility
SGF ] to be interconnected consistent with safety, reliability, and
power quality standards under the Level 2 process, the utility shall forward an
executable interconnection agreement to the [ interconnection
customer IC ] within 10 business days [ after
the determination ] that requires the [ interconnection
customer IC ] to pay the costs of such system
modifications prior to interconnection.
4. If not, the interconnection request will [ continue
to ] be [ evaluated under elevated to ]
the Level 3 [ study interconnection ] process.
20VAC5-314-70. Level 3 interconnection process.
A. The Level 3 interconnection process shall be used by an
[ IC interconnection customer ] proposing to
interconnect a small generating facility with the [ utility's
distribution utility ] system if the [ small
generating facility SGF ] is [ (i) larger
than 2 MW but ] no larger than 20 MW [ , (ii)
not certified, or (iii) certified but did and does ] not
pass [ or qualify for ] the Level 1 or Level 2
interconnection [ process processes ].
[ A study process consisting of As needed, a ] scoping
[ meeting ], feasibility [ study ],
system impact [ study ], and facilities [ study ]
shall precede the preparation of [ an interconnection
agreement a Small Generator Interconnection Agreement (Schedule 6 of
20VAC5-314-170) ]. [ Feasibility studies, scoping
studies, and facility Any of the ] studies may be
combined [ for simpler projects ] by mutual
agreement of the [ utility and the ] parties.
B. Scoping [ study meeting ].
1. A scoping meeting will be held within 10 business days
after the [ interconnection request Interconnection
Request Form ] is deemed complete, or as otherwise mutually agreed
to by the parties. The utility and the [ interconnection
customer IC ] shall bring to the meeting personnel,
including system engineers and other resources as may be reasonably required to
accomplish the purpose of the meeting.
2. The purpose of the scoping meeting is to discuss the
interconnection request. The parties shall [ further ]
discuss [ whether the utility should perform a feasibility
study or proceed directly to a system impact study, or a facilities study,
or an interconnection agreement the studies and the cost responsibilities
for the studies ]. [ If the parties agree that a
feasibility study should be performed, the utility shall provide the
interconnection customer, as soon as possible, but not later than five business
days after the scoping meeting, a feasibility study agreement including an
outline of the scope of the study and a nonbinding good faith estimate of the
cost to perform the study. ]
3. The scoping meeting may be omitted by mutual agreement.
[ In order to remain in consideration for interconnection, an
interconnection customer who has requested a feasibility study must return the
executed feasibility study agreement within 15 business days. If the parties
agree not to perform a feasibility study, the utility shall provide the
interconnection customer, no later than five business days after the scoping
meeting, a system impact study agreement including an outline of the scope of
the study and a nonbinding good faith estimate of the cost to perform the
study. ]
C. Feasibility study.
[ 1. If the parties agree that a feasibility study should be performed, the utility shall provide the IC with a feasibility study agreement, including an outline of the scope of the feasibility study and an estimate of the cost to perform the study no later than five business days after the scoping meeting or five business days after the decision is made to not have a scoping meeting.
If the parties agree to not perform a feasibility study, the utility shall provide the IC a system impact study agreement including an outline of the scope of the study and an estimate of the cost to perform the study no later than five business days after the scoping meeting, or five business days after the decision is made to not have a scoping meeting.
2. To maintain its position in the utility’s interconnection queue, the IC must execute the feasibility study agreement and return it to the utility along with the deposit for the feasibility study within 15 business days after receipt of the agreement. If the IC fails to return the executed feasibility study agreement along with the deposit within 15 business days after receipt of the agreement, the interconnection request shall be deemed withdrawn and the interconnection request shall lose its place in the utility’s interconnection queue. ]
[ 1. 3. ] A feasibility
study shall identify any potential adverse system impacts that would result
from the interconnection of the [ small generating facility
SGF ].
[ 2. 4. ] A deposit of
[ the lesser of no more than ] 50% of the
[ good faith ] estimated feasibility study costs or
earnest money of $1,000 may be required from the interconnection customer.
a. [ Any study fees Study costs ]
shall be [ based on ] the [ distribution
company's utility’s ] actual [ incremental ]
costs and will be invoiced to the [ interconnection
customer IC ] after the study is completed and delivered and
will include a summary of professional time.
b. The [ interconnection customer must
IC shall ] pay any study costs that exceed the deposit without
interest within 30 calendar days on receipt of the invoice or resolution of any
dispute. If the deposit exceeds the invoiced fees, the [ distribution
company utility ] shall refund such excess within 30
calendar days of the invoice without interest.
[ 3. 5. ] The feasibility
study shall be based on the technical information provided by the [ interconnection
customer IC ] in the [ interconnection
request Interconnection Request Form ], as may be
modified as the result of the scoping meeting. The [ distribution
company utility ] reserves the right to request
additional technical information from the [ interconnection
customer IC ] as may reasonably become necessary
consistent with [ Good Utility Practice ] during the
course of the feasibility study and as designated in accordance with the
standard small generator interconnection procedures. [ All
modification made to the interconnection request shall be made in writing to
the utility. ] If the interconnection customer modifies its
interconnection request, the time to complete the feasibility study may be
extended by agreement of the parties.
[ 4. 6. ] In performing the
[ feasibility ] study, the [ distribution
company utility ] shall rely, to the extent reasonably
practicable, on recent studies. The [ interconnection
customer IC ] shall not be charged for such existing
studies; however, the [ interconnection customer IC ]
shall be responsible for charges associated with any new study or
modifications to existing studies that are reasonably necessary to perform the
feasibility study.
[ 5. 7. ] The feasibility
study report shall provide the following analyses for the purpose of
identifying any potential adverse system impacts that would result from the
interconnection of the [ small generating facility as proposed
SGF ]:
a. Initial identification of any circuit breaker short
circuit capability limits exceeded [ as a result of the
interconnection ];
b. Initial identification of any thermal overload or
voltage limit violations [ resulting from the interconnection ];
c. Initial review of grounding requirements and electric system protection; and
d. Description and [ nonbonding ]
estimated cost of facilities [ and estimated construction time ]
required to interconnect the [ proposed small generating
facility SGF ] and to address the identified short
circuit and power flow issues.
[ 6. 8. ] The feasibility
study shall model the impact of the [ small generating facility
regardless of purpose SGF for all purposes identified in the
Interconnection Request Form ] in order to avoid the further
expense and interruption of operation for reexamination of feasibility and
impacts if the [ interconnection customer IC ]
later changes the purpose for which the [ small generating
facility SGF ] is being installed.
[ 7. 9. ] The [ feasibility ]
study shall include the feasibility of [ any interconnection
at a proposed project site where there could be multiple all ]
potential points of interconnection, as requested by the [ interconnection
customer IC ] and at the [ interconnection
customer's IC’s ] cost.
[ 8. Once the feasibility study is completed, a
10. A ] feasibility study report shall be prepared and transmitted
to the [ interconnection customer. Barring unusual
circumstances, the feasibility study must be completed and the feasibility
study report transmitted IC ] within 30 business days of the
[ interconnection customer's agreement to conduct a
feasibility study utility’s receipt of the complete executed feasibility
study agreement and required deposit ].
[ 9. 11. ] If the feasibility
study shows no potential for adverse system impacts, [ then within
five business days ] the utility shall send the [ interconnection
customer IC either an executable Small Generator Interconnection
Agreement (Schedule 5, 20VAC5-314-170) or ] a facilities study
agreement, including an outline of the scope of the study and [ a
nonbinding good faith an ] estimate of the cost to
perform the study.
[ 10. 12. ] If the
feasibility study shows [ the ] potential for
adverse system impacts, the review process shall proceed to the [ appropriate ]
system impact study [ or studies ].
D. System impact study.
[ 1. No later than five business days after the parties agree that a system impact study should be performed, the utility shall provide the IC a system impact study agreement including an outline of the scope of the system impact study and an estimate of the cost to perform the study.
2. To maintain its position in the utility’s interconnection queue, the IC must execute the system impact study agreement and return it to the utility along with the deposit for the system impact study within 15 business days after receipt of the agreement. If the IC fails to return the executed system impact study agreement along with the deposit within 15 business days after receipt of the agreement, the interconnection request shall be deemed withdrawn and the interconnection request shall lose its place in the utility’s interconnection queue.
3. A deposit equal to the estimated cost of a system impact study may be required from the IC.
a. Study cost shall be the utility’s actual incremental costs and will be invoiced to the IC after the study is completed and delivered and will include a summary of professional time.
b. The IC shall pay any study costs that exceed the deposit within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the utility shall refund the excess within 30 calendar days of the invoice without interest. ]
[ 1. 4. ] A system impact
study shall identify and detail the electric system impacts that would result
if the [ proposed small generating facility
SGF ] were interconnected without project modifications or electric
system modifications, focusing on the adverse [ electric ]
system impacts identified in the feasibility study, or [ to
study potential impacts, including but not limited to those identified ]
in the scoping meeting. A system impact study shall evaluate the impact of
the proposed interconnection on the reliability of the electric system.
[ 2. 5. ] A system impact
study will be based upon the results of the feasibility study and the technical
information provided by the interconnection customer in the interconnection
request. The [ distribution company utility ]
reserves the right to request additional technical information from the
[ interconnection customer IC ] as may
reasonably become necessary consistent with [ Good Utility Practice ]
during the course of the system impact study. If the [ interconnection
customer IC ] modifies its designated point of
interconnection, [ or ] interconnection request, or the
technical information provided therein [ is modified ],
the time to complete the system impact study may be extended.
[ 3. 6. ] A system impact
study shall consist of a [ study of the potentially impacted
transmission and distribution systems, a ] short circuit analysis,
a stability analysis, a power flow analysis, voltage drop and flicker studies,
[ protection and set point coordination studies, and ] grounding
reviews, [ distribution load flow study, analysis of equipment
interrupting ratings, protection coordination study, and impacts on electric
system operation, ] as necessary. A system impact study shall state
the assumptions upon which it is based, state the results of the analyses, and
provide the requirement or potential impediments to providing the requested
interconnection service, including a preliminary indication of the cost and
length of time that would be necessary to correct any problems identified in
those analyses and implement the interconnection. A system impact study shall
provide a list of facilities [ and modifications ] that
[ are would be ] required as a result of the
interconnection [ request and nonbinding good faith
along with ] estimates of cost responsibility and time to
construct. [ If arranged with the utility prior to the utility
preparing the system impact study agreement, the system impact study may, at
the IC’s cost, include one or more alternatives to the point of
interconnection; however, such alternative points must be on the same
distribution circuit as the point of interconnection the IC specified as the
proposed point of interconnection. ]
[ 4. A distribution system impact study shall
incorporate a distribution load flow study, an analysis of equipment
interrupting ratings, protection coordination study, voltage drop and flicker
studies, protection and set point coordination studies, grounding reviews, and
the impact on electric system operation, as necessary.
5. 7. ] Affected systems may
participate in the preparation of a system impact study, with a division of
costs among such entities as they may agree. All affected systems shall be
afforded an opportunity to review and comment upon a system impact study that
covers potential adverse system impacts on their electric systems, and the
[ distribution company utility ] has 20
additional business days to complete a system impact study requiring review by
affected systems.
[ 6. 8. ] If the utility
uses a queuing procedure for sorting or prioritizing projects and their
associated cost responsibilities for any required network upgrades, the system
impact study shall consider all generating facilities (and with respect to
clause iii below, any identified upgrades associated with such higher queued interconnection)
that, on the date the system impact study is commenced are: (i) directly
interconnected with the [ distribution company's electric
utility ] system; or (ii) interconnected with affected systems and
may have an impact on the proposed interconnection; and (iii) have a pending
higher queued interconnection request to interconnect with the [ utility's
electric utility ] system.
[ 7. 9. ] A [ distribution ]
system impact study, if required, shall be completed and the results
transmitted to the [ interconnection customer IC ]
within [ 30 45 ] business days after
an agreement is signed by the parties [ . A transmission system
impact study, if required, shall be completed and the results transmitted to
the interconnection customer within 45 business days after an agreement is
signed by the parties ], or in accordance with the utility's
queuing procedures.
[ 8. A deposit of the equivalent of the good faith
estimated cost of a distribution system impact study and one-half of the good
faith estimated cost of a transmission system impact study may be required from
the interconnection customer.
9. Any study fees shall be based on the utility's actual
costs and will be invoiced to the interconnection customer after the study is
completed and delivered and will include a summary of professional time.
10. The interconnection customer shall pay any study
costs that exceed the deposit within 30 calendar days on receipt of the invoice
or resolution of any dispute. If the deposit exceeds the invoiced fees, the
utility shall refund such excess within 30 calendar days of the invoice.
Interest shall not apply.
11. If no transmission system impact study is required,
adverse distribution system impacts are identified in the scoping meeting or
shown in the feasibility study, a distribution system impact study shall be
performed. The utility shall send the interconnection customer a distribution
system impact study agreement within 15 business days of transmittal of the
feasibility study report, including an outline of the scope of the study and a
nonbinding good faith estimate of the cost to perform the study, or following
the scoping meeting if no feasibility study is to be performed.
12. In instances where the feasibility study or the
distribution system impact study shows potential for transmission system
adverse system impacts, within five business days following transmittal of the
feasibility study report, the utility shall send the interconnection customer a
transmission system impact study agreement, including an outline of the scope
of the study and a nonbinding good faith estimate of the cost to perform the
study, if such a study is required.
13. If a transmission system impact study is not
required, but adverse distribution system impacts are shown by the feasibility
study to be possible and no distribution system impact study has been
conducted, the utility shall send the interconnection customer a distribution
system impact study agreement.
14. If the feasibility study shows no potential for
transmission system or distribution system adverse impacts, the utility shall
send the interconnection customer either an executable Small Generator
Interconnection Agreement (SGIA) included in this chapter as Schedule 5 in
20VAC5-314-170, or a facilities study agreement, including an outline of the
scope of the study and a nonbinding good faith estimate of the cost to perform
the study, as applicable.
15. In order to remain under consideration for
interconnection, the interconnection customer shall return executed system
impact study agreements, if applicable, within 30 business days.
10. If the system impact study shows that facility modifications are needed to accommodate the SGF, then within five business days following transmittal of the system impact study report, the utility shall send the IC a facilities study agreement, including an outline of the scope of the study and an estimate of the cost to perform the study.]
E. Facilities study.
1. [ Once the required system impact study
(or studies) is completed, a system impact study report shall be prepared and
transmitted to the interconnection customer along with a facilities study
agreement within five business days, including an outline of the scope of the
study and a nonbinding good faith estimate of the cost to perform the facilities
study. In the case where one or both impact studies are determined to be
unnecessary, a notice of the fact shall be transmitted to the interconnection
customer within the same timeframe. The facilities study shall
specify and estimate the cost of the equipment, engineering, procurement, and
construction work needed to implement the conclusion of the feasibility and/or
system impact study and to allow SGF to be interconnected and operate safely
and reliably. ]
[ 2. In order to remain under consideration for
interconnection, or, as appropriate, in the utility's interconnection queue,
the interconnection customer shall provide the following information, or a
request for an extension of time within 30 business days, and the facilities
study shall be based on the responses of the IC to the following queries:
a. Provide a location plan and simplified one-line
diagram of the plant and station facilities. For staged projects, please
indicate future generation, transmission circuits, etc. On the one-line diagram,
indicate the generation capacity attached at each metering location. (Maximum
load on CT (current transformer)/PT (partial transformer) On the one-line
diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps
b. One set of metering is required for each generation
connection to the new ring bus or existing distribution company station.
Number of generation connections: _____________________
c. Will an alternate source of auxiliary power be
available during CT/PT maintenance?
Yes ___________ No ___________
d. Will a transfer bus on the generation side of the
metering require that each meter set be designed for the total plant
generation?
Yes ___________ No ___________ (Please indicate on the
one-line diagram).
e. What type of control system or Programmable Logic
Controller (PLC) will be located at the small generating facility?
______________________________________________
f. What protocol does the control system or PLC use?
______________________________________________
g. Provide a 7.5-minute quadrangle map of the site.
Indicate the plant, station, transmission line, and property lines.
h. Physical dimensions of the proposed interconnection
station: ______________________________________________
i. Bus length from generation to interconnection
station: ______________________________
j. Line length from interconnection station to utility's
transmission system. ________________________________________
k. Tower number observed in the field. (Painted on tower
leg)*: ______________________________________________
l. Number of third party easements required for
transmission lines*: ______________________________________________
*To be completed in coordination with distribution
company.
m. Is the small generating facility located in utility's
service area? Yes ___________ No___________;
If No, please provide name of local provider:
______________________________________________
n. Please provide the following proposed schedule dates:
Begin Construction Date:____________________________
Generator step-up transformers receive back feed power
date: ___________________
Generation Testing Date:____________________________
Commercial Operation Date:____________________________
3. The facilities study shall specify and estimate the
cost of the equipment, engineering, procurement, and construction work
(including overheads) needed to implement the conclusions of the system impact
study or studies.
4. A deposit of the good faith estimated facilities
study costs may be required from the interconnection customer.
5. Any study fees shall be based on the distribution
company's actual costs and will be invoiced to the interconnection customer
after the study is completed and delivered and will include a summary of
professional time.
6. The interconnection customer shall pay any study
costs that exceed the deposit within 30 calendar days on receipt of the invoice
or resolution of any dispute. If the deposit exceeds the invoiced fees, the
distribution company shall refund such excess within 30 calendar days of the
invoice. Interest shall not apply.
2. To maintain its position in the utility’s interconnection queue, the IC must execute the facilities study agreement and return it to the utility along with a completed Facilities Study Information Form (Schedule 5, 20VAC5-314-170) and deposit for the facilities study within 30 business days after receipt of the agreement, unless an extension has been agreed to with the utility. Otherwise, the interconnection request shall be deemed withdrawn and the interconnection request shall lose its place in the utility’s interconnection queue.
3. A deposit equal to the estimated cost of a facilities study may be required from the IC.
a. Study cost shall be the utility’s actual incremental costs and will be invoiced to the IC after the study is completed and delivered and will include a summary of professional time.
b. The IC shall pay any study costs that exceed the deposit within 30 calendar days after receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the utility shall refund the excess within 30 calendar days of the invoice without interest. ]
[ 7. 4. ] Design for any
required [ customer’s ] interconnection facilities
[ , attachment facilities, ] and/or upgrades shall be
performed under the facilities study [ agreement ].
The utility may contract with consultants to perform activities required under
the facilities study [ agreement ]. The
[ interconnection customer IC ] and the
utility may agree to allow the [ interconnection customer
IC ] to separately arrange for the design of some of the
[ customer’s ] interconnection facilities. In such cases,
facilities design will be reviewed and/or modified prior to acceptance by the
utility, under the provisions of the facilities study [ agreement ].
If the parties agree to separately arrange for design and construction, and
provided security and confidentiality requirements can be met, the utility
shall make sufficient information available to the [ interconnection
customer IC ] in accordance with confidentiality and
critical infrastructure requirements [ , ] to permit
the [ interconnection customer IC ] to
obtain an independent design and cost estimate for any necessary facilities.
[ 8. 5. ] The facilities
study shall [ specify and estimate the cost of the equipment,
engineering, procurement and construction work (including overheads) needed to
implement the conclusions of the system impact study or studies. The facilities
study shall also ] identify (i) the electrical switching
configuration of the equipment, including, without limitation, transformer,
switchgear, meters, and other station equipment, (ii) the nature and estimated
cost of the [ utility's interconnection
attachment ] facilities and [ distribution ] upgrades
necessary to accomplish the interconnection, and (iii) an estimate of the time
required to complete the construction and installation of such facilities.
[ 9. 6. ] The utility may
propose to group facilities required for more than one [ interconnection
customer IC ] in order to minimize facilities costs
through economies of scale, but any [ interconnection customer
IC ] may require the installation of facilities required for its
own small generating facility if it [ is willing to pay
pays ] the costs of those facilities.
[ 10. Once the facilities study is completed, a
facilities study report shall be prepared and transmitted to the
interconnection customer. Barring unusual circumstances, the facilities study
must be completed and the facilities study report transmitted within 30
business days of the interconnection customer's agreement to conduct a
facilities study 11. In cases where upgrades are required, the facilities study
must be completed within 45 business days of the receipt of this facilities
study agreement. In cases where no upgrades are necessary, and the required
facilities are limited to interconnection facilities, the facilities study must
be completed within 30 business days.
7. In cases where system upgrades are required, the utility shall transmit the facilities study report within 45 business days after receipt of the complete facilities study agreement, Facilities Study Information Form, and the deposit. In cases where no system upgrades are necessary, and the required facilities are limited to customer’s interconnection facilities and attachment facilities only, the utility shall transmit the facilities study report within 30 business days after receipt of the complete facilities study agreement, Facilities Study Information Form and the deposit. ]
F. [ Interconnection agreement
Small Generator Interconnection Agreement ].
1. [ Upon completion of the facilities
study, and with the agreement of the interconnection customer to pay for
interconnection facilities and upgrades identified in the facilities study, the
utility shall provide the interconnection customer an executable SGIA within
five business days Within five business days after transmittal of
the final study (i.e. the facilities study, or if applicable, a combined study
that satisfies all study requirements), the utility shall provide the
interconnection customer an executable SGIA (Schedule 6, 20VAC5-314-170) ].
2. After receiving [ an interconnection
agreement the SGIA ] from the utility, the [ interconnection
customer IC ] shall have 30 business days or another
mutually agreeable [ time frame deadline, ] to
sign and return the [ interconnection agreement, or request that
the utility file an unexecuted interconnection agreement with the commission
SGIA ]. If the [ interconnection customer
IC ] does not [ sign return ] the
[ interconnection agreement, or ask that it be filed unexecuted by
the utility within 30 business days SGIA within the deadline ],
the interconnection request shall be deemed withdrawn [ and the IC
shall lose its place in the utility’s queue ]. After the
[ interconnection agreement SGIA ] is signed
by the parties, the interconnection of the [ small generating
facility SGF ] shall proceed under the provisions of the
SGIA.
20VAC5-314-80. Interconnection metering.
Any metering necessitated by the use of the small generating facility shall be installed at the interconnection customer's expense in accordance with commission requirements or the utility's specifications.
20VAC5-314-90. Commissioning tests.
Commissioning tests of the interconnection customer's
installed equipment shall be performed pursuant to applicable codes and
standards, including IEEE 1547.1 2005 "IEEE Standard Conformance Test
Procedures for Equipment Interconnecting Distributed Resources with Electric
Power Systems." The utility shall be given at least five business days
written notice, or notice as otherwise mutually agreed to by the parties, of
the tests and [ may the utility shall ] be
[ allowed to be ] present to witness the commissioning
tests. The utility shall [ not ] be compensated by the
[ interconnection customer IC ] for
[ its expense in ] witnessing [ Level
2 and Level 3 ] commissioning tests.
20VAC5-314-100. Disputes.
A. The parties agree to attempt to resolve all disputes arising out of the interconnection process according to the provisions of this section.
B. In the event of a dispute, either party shall provide
the other party with a written notice of dispute. The notice shall describe in
detail the nature of the dispute. [ If the dispute has not been
resolved within five business days after receipt of the notice, either party
may contact a mutually agreed upon third party dispute resolution service for
assistance in resolving the dispute The parties shall make a good
faith effort to resolve the dispute informally within 10 business days ].
C. [ If the dispute has not been resolved within 10 business days after receipt of the notice, either party may seek resolution assistance from the commission’s Division of Energy Regulation where the matter will be handled as an informal complaint. If that process is unsatisfactory, either party may petition the commission to handle the dispute as a formal complaint.
Alternatively, the parties may seek resolution through the assistance of a dispute resolution service. ] The dispute resolution service will assist the parties in either resolving the dispute or in selecting an appropriate dispute resolution venue (e.g., mediation, settlement judge, early neutral evaluation, or technical expert) to assist the parties in resolving their dispute. [ Each party agrees to conduct all negotiations in good faith and will be responsible for one half of any costs paid to neutral third parties. ]
[ D. Each party agrees to conduct all negotiations
in good faith and will be responsible for 1/2 of any costs paid to neutral
third parties.
E. D. ] If [ neither
party elects to seek assistance from the dispute resolution service, or if the ]
attempted dispute resolution fails [ to satisfy one or both of
the parties ] , then either party may exercise whatever rights and
remedies it may have in equity or law consistent with the terms of the
[ agreements between the parties or it may seek resolution at the
commission agreement ].
20VAC5-314-110. Confidential information.
A. Confidential information shall mean any confidential
and/or proprietary information provided by one party to the other party that is
clearly marked or otherwise designated "Confidential." All design,
operating specifications, and metering data provided by the [ interconnection
customer IC ] shall be deemed confidential information
regardless of whether it is clearly marked or otherwise designated as such.
B. Confidential information does not include information previously in the public domain, required to be publicly submitted or divulged by governmental authorities (after notice to the other party and after exhausting any opportunity to oppose such publication or release), or necessary to be divulged in an action to enforce an agreement between the parties. Each party receiving confidential information shall hold such information in confidence and shall not disclose it to any third party nor to the public without the prior written authorization from the party providing that information, except to fulfill obligations under agreements between the parties, or to fulfill legal or regulatory requirements.
1. Each party shall employ at least the same standard of care to protect confidential information obtained from the other party as it employs to protect its own confidential information.
2. Each party is entitled to equitable relief, by injunction or otherwise, to enforce its rights under this section to prevent the release of confidential information without bond or proof of damages, and may seek other remedies available at law or in equity for breach of this provision.
C. Notwithstanding anything in this chapter to the
contrary, if the commission, during the course of an investigation or
otherwise, requests information from one of the parties that is otherwise
required to be maintained in confidence, the party shall provide the requested
information to the commission, within the time provided for in the request for
information. In providing the information to the commission, the party may
request that the information be treated as confidential and nonpublic by the
commission and that the information be withheld from public disclosure. Parties
are prohibited from notifying the other party prior to the release of the
confidential information to the commission. [ The party shall
notify the other party when it is notified by the commission that a request to
release confidential information has been received by the commission, at which
time either of the parties may respond before such information would be made
public. ]
20VAC5-314-120. [ Comparability
Equal treatment ].
The utility shall receive, process, and analyze all
interconnection requests in a timely manner as set forth in this chapter. The
utility shall use the same reasonable efforts in processing and analyzing
interconnection requests from all Interconnection customers, whether the
[ small generating facility SGF ] is owned or
operated by the utility, its subsidiaries or affiliates, or others.
20VAC5-314-130. Record retention.
The utility shall maintain, subject to audit, records for three years of (i) all interconnection requests received pursuant to this chapter, (ii) the times required to complete interconnection request approvals and disapprovals, and (iii) justification for the actions taken on the interconnection requests.
20VAC5-314-140. Coordination with affected systems.
The utility shall coordinate the conduct of any studies
required to determine the impact of the [ interconnection
request small generating facility ] on affected systems
with affected system operators and, if possible, include those results (if
available) in its applicable interconnection [ study
studies ] within the time frame specified in this chapter. The
utility will include such affected system operators in all meetings held with
the [ interconnection customer IC ] as
required by this chapter. The [ interconnection customer
IC ] shall cooperate with the utility in all matters related to the
conduct of studies and the determination of modifications to affected systems.
A utility [ which that ] may be an
affected system shall cooperate with the utility with [ whom
which ] interconnection has been requested in all matters related
to the conduct of studies and the determination of modifications to affected
systems. [ The utility owning or operating the system to which the
IC desires to interconnect shall not be held responsible or liable for any
delays in the interconnection process attributable to the lack of information
or cooperation from the owners or operators of affected systems. ]
20VAC5-314-150. Capacity of the small generating facility.
A. If the interconnection request is for an increase in
capacity for an existing small generating facility, the interconnection request
shall be evaluated on the basis of the new total capacity of the [ small
generating facility SGF ].
B. If the interconnection request is for a [ small
generating facility SGF ] that includes multiple energy
production devices at a site for which the interconnection customer seeks a
single point of interconnection, the interconnection request shall be evaluated
on the basis of the aggregate capacity of the multiple devices.
C. The interconnection request shall be evaluated using
the maximum rated capacity of the [ small generating facility
SGF ].
20VAC5-314-160. Insurance.
A. For [ systems of 500 kW or less
a small generating facility with a rated capacity not exceeding 10 kW ],
the IC, at its own expense, shall secure and maintain in effect during the term
of the agreement liability insurance with a combined single limit for bodily
injury and property damage of not less than [ $300,000
$100,000 ] for each occurrence.
[ For an SGF with a rated capacity exceeding 10 kW but not exceeding 500 kW, the IC, at its own expense, shall secure and maintain in effect during the term of the agreement liability insurance with a combined single limit for bodily injury and property damage of not less than $300,000 for each occurrence. ]
For [ systems greater than an
SGF with a rated capacity exceeding ] 500 kW but [ smaller
than not exceeding ] 2 MW, the IC, at its own expense,
shall secure and maintain in effect during the term of the agreement liability
insurance with a combined single limit for bodily injury and property damage of
not less than $2 million for each occurrence. Insurance coverage for
[ systems greater than an SGF with a rated capacity
exceeding ] 2 MW shall be determined on a case-by-case basis
[ by the utility ] and shall reflect the size of the
installation and the potential for system damage.
B. Except for those [ photovoltaic
inverter-based ] systems [ installed on a
residential premise ] that have a [ design
rated ] capacity of 500 kW or less, the utility shall be named as
an additional insured by endorsement to the insurance policy and the policy
shall provide that written notice be given to the utility at least 30 days
prior to any cancellation or reduction of any coverage. Such liability
insurance shall provide, by endorsement to the policy, that the utility shall
not by reason of its inclusion as an additional insured incur liability to the insurance
carrier for the payment of premium of such insurance. For all [ photovoltaic
inverter-based ] systems, the liability insurance shall not exclude
coverage for any incident related to the subject generator or its operation.
C. Certificates of insurance evidencing the requisite
coverage and provision shall be furnished to [ a the ]
utility prior to the date of interconnection of the [ small
generating facility SGF ]. [ Utilities
The utility ] shall be permitted to periodically obtain proof of
current insurance coverage form the [ producer IC ]
in order to verify [ continuing ] proper liability
insurance coverage. [ The ] IC will not be allowed to
commence or continue interconnected operations unless evidence is provided that
[ satisfactory required ] insurance coverage
is in effect at all times.
20VAC5-314-170. Schedules for Chapter 314.
The following schedules shall be used in the administration of this chapter.
Schedule 1
LEVEL 1 INTERCONNECTION
REQUEST FORM FOR SMALL GENERATING FACILITY [ LESS THAN
NOT EXCEEDING ] 500 kW
PURSUANT TO 20VAC5-314-40 OF THE COMMISSION'S REGULATIONS GOVERNING INTERCONNECTION OF SMALL ELECTRIC GENERATORS, APPLICANT HEREBY GIVES NOTICE OF INTENT TO OPERATE A GENERATING FACILITY.
Section 1. [ Applicant
Interconnection Customer ] Information
Name:____________________________________________________________ |
Mailing Address:____________________________________________________ |
[ City, State, Zip: _________________________________________________] |
Street Address: __________________________________________________ |
[ City, State, Zip: _________________________________________________] |
Phone Number(s): ___________________________________________________ |
Fax Number: _____________________________ Email
[ |
[ |
|
[ |
Energy Service Provider [ |
[ |
Proposed Interconnection Date:_________________________________________ |
|
[ Section 2. Processing Fee or Deposit
The nonrefundable processing fee payable to the utility is $100. ]
Section [ 2. 3. Small ]
Generating Facility Information
[ |
SGF owner: _____________________________________________________ |
SGF operator: ___________________________________________________ ] |
Business relationship to applicant: _______________________________________ |
Mailing address: ______________________________________________________ |
[ City, State, Zip:__________________________________________________ ] |
[ |
[ City, State, Zip: _________________________________________________ ] |
Phone Number(s): ____________________________________________________ |
Fax Number: ______________________________ Email
[ |
Fuel Type:____________________________________________________________ |
Generator Manufacturer and Model: ______________________________________ |
Rated Capacity in kilowatts: AC: _________________________ DC: ____________ |
Inverter Manufacturer and Model:_________________________________________ |
Battery Backup [ |
|
Section [ 3 4 ].
Information for Generators with an AC capacity in excess of 25 [ kilowatts
kW ]
Is the proposed generator inverter based? Yes ____ No ____
Generator Type [ (circle one) ]:
Inverter [ ]
Induction [
] Synchronous [ ]
Frequency: ____________ Hz; Number of phases [ (circle
one) ] : One [ ]
Three [ ]
Rated Capacity: DC _________KW; AC apparent ___________ KVA; AC real _________ KW;
Power factor ____________%; AC voltage _________; AC amperage___________
Facility schematic and equipment layout must be attached to this form.
Section [ 4. 5. ] Vendor
Certification
The [ |
Signed (Vendor): ______________________________________________ Date: __________ |
Name (printed): _______________________________________________________________ |
Company: ___________________________________________________________________ |
Phone Number: _______________________________ |
Mailing Address:_______________________________________________________________ |
[ City, State, Zip: _________________________________________________ ] |
Section [ 5. 6. ] Electrician
Certification
The [ |
Signed (Licensed Electrician): ___________________________ Date: ______ |
Name (printed): ___________________________________________________ |
License Number: __________________________ Phone Number: ___________ |
Mailing Address: ____________________________________________________ |
[ City, State, Zip:__________________________________________________ ] |
[ |
|
[ Section 7. Applicant Signature ]
|
I hereby certify that, to the best of my knowledge, all of the information provided in this Request Form is true and correct. |
Signature of Applicant: _____________________________________________ |
Date:________________________
|
[ Section 8. Utility Acknowledgement of Receipt |
Signed: _______________________________________________________ |
Title:__________________________________________________________ |
Utility: ________________________________________________________ |
Date:______________________________ |
Utility signature signifies only receipt of this form, in compliance with 20VAC5-314-40, the State Corporation Commission's Regulations Governing Interconnection of Small Electrical Generators. ] |
Schedule 2
Certification of Small Generator Equipment Packages
Small generating facility equipment proposed for use separately or packaged with other equipment in an interconnection system shall be considered certified for interconnected operation if (i) it has been tested in accordance with industry standards for continuous utility interactive operation in compliance with the appropriate codes and standards referenced below by any Nationally Recognized Testing Laboratory (NRTL) recognized by the United States Occupational Safety and Health Administration to test and certify interconnection equipment pursuant to the relevant codes and standards listed in SGIP Schedule 3, (ii) it has been labeled and is publicly listed by such NRTL at the time of the interconnection application, and (iii) such NRTL makes readily available for verification all test standards and procedures it utilized in performing such equipment certification, and, with consumer approval, the test data itself. The NRTL may make such information available on its website and by encouraging such information to be included in the manufacturer's literature accompanying the equipment.
The interconnection customer must verify that the intended use of the equipment falls within the use or uses for which the equipment was tested, labeled, and listed by the NRTL.
Certified equipment shall not require further type-test review, testing, or additional equipment to meet the requirements of this interconnection procedure; however, nothing herein shall preclude the need for an on-site commissioning test by the parties to the interconnection nor follow up production testing by the NRTL.
If the certified equipment package includes only interface
components (switchgear, inverters, or other interface devices), then an
[ interconnection customer IC ] must show
that the generator or other electric source being utilized with the equipment
package is compatible with the equipment package and is consistent with the
testing and listing specified for this type of interconnection equipment.
Provided the generator or electric source, when combined
with the equipment package, is within the range of capabilities for which it
was tested by the NRTL, and does not violate the interface components' labeling
and listing performed by the NRTL, no further design review, testing or
additional equipment on the customer side of the point of [ common
coupling interconnection ] shall be required to meet the
requirements of this interconnection procedure.
An equipment package does not include equipment provided by the utility.
Schedule 3
Certification Codes and Standards
IEEE1547 Standard for Interconnecting Distributed Resources with Electric Power Systems (including use of IEEE 1547.1 testing protocols to establish conformity)
UL 1741 Inverters, Converters, and Controllers for Use in Independent Power Systems
IEEE Std 929-2000 IEEE Recommended Practice for Utility Interface of Photovoltaic (PV) Systems
NFPA 70 (2005), National Electrical Code
IEEE Std C37.90.1-1989 (R1994), IEEE Standard Surge Withstand Capability (SWC) Tests for Protective Relays and Relay Systems
IEEE Std C37.90.2 (1995), IEEE Standard Withstand Capability of Relay Systems to Radiated Electromagnetic Interference from Transceivers
IEEE Std C37.108-1989 (R2002), IEEE Guide for the Protection of Network Transformers
IEEE Std C57.12.44-2000, IEEE Standard Requirements for Secondary Network Protectors
IEEE Std C62.41.2-2002, IEEE Recommended Practice on Characterization of Surges in Low Voltage (1000V and Less) AC Power Circuits
IEEE Std C62.45-1992 (R2002), IEEE Recommended Practice on Surge Testing for Equipment Connected to Low-Voltage (1000V and Less) AC Power Circuits
ANSI C84.1-1995 Electric Power Systems and Equipment – Voltage Ratings (60 Hertz)
IEEE Std 100-2000, IEEE Standard Dictionary of Electrical and Electronic Terms
NEMA MG 1-1998, Motors and Small Resources, Revision 3
IEEE Std 519-1992, IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems
NEMA MG 1-2003 (Rev 2004), Motors and Generators, Revision 1
Schedule 4
[ LEVEL LEVELS ] 2 AND 3
INTERCONNECTION REQUEST FORM [ FOR ] SMALL
GENERATING [ FACILITIES FACILITY ] LESS
THAN 20 MW
[ Distribution
Company:________________________________________
Designated Contact Person:
________________________________________
Address: ________________________________________________
Telephone Number: ____________________
Fax:________________________________
E-Mail Address:
________________________________________________
An Interconnection Request is considered complete when
it provides all applicable and correct information required below.
Processing Fee or Deposit
If the Interconnection Request is submitted as Level 2,
the nonrefundable processing fee payable to the distribution company is $500.
If the interconnection request is submitted as Level 3,
the interconnection customer shall submit to the distribution company a deposit
not to exceed $1,000 towards the cost of the feasibility study.
Interconnection Customer Information
Legal Name of the Interconnection Customer (or, if an
individual, individual's name)
Name:___________________________________________
Account Number:
________________________________________________
Contact
person:__________________________________________
Mailing
Address:_________________________________________
City: State: Zip:_____________________________________________
Facility location (if different from
above):_______________________________
Telephone (Day): __________________ Telephone (Evening):
_____________
Fax: _________________________ E-Mail
Address:_____________________
Alternative contact information (if different from the
interconnection customer)
Contact Name:
________________________________________________
Title: ________________________________________________
Address:_________________________________________
________________________________________________
Telephone (Day): ________________ Telephone (Evening):
________________
Fax: __________________________ E-Mail Address:
____________________
|
|
||
|
|||
|
|||
|
|||
|
|
||
|
|||
|
|
|
|
Contact Name:
________________________________________________
Title: ________________________________________________
Address:
________________________________________________
Telephone (Day): _________________ Telephone (Evening):
______________
Fax: ________________ E-Mail Address: _____________
Requested point of interconnection:
____________________________________
Interconnection customer's requested in-service date:
______________________
Section 1. Interconnection Customer Information
Name:
Contact person:
Mailing address:
City: State: Zip:
Utility and account number:
Energy Service Provider and account number:
Facility address:
Telephone (Day): ___________ (Evening):
Fax: _______________ E-Mail:
Alternative contact information
Contact Name:
Title:
Mailing Address: ________________________________________________
City: State: Zip:
Telephone (Day): __________ (Evening):
Fax: __________________ E-Mail:
Application is for: New Small Generating Facility ______ Capacity addition ______
If capacity addition to existing facility, please describe:
The Small Generating Facility will supply: Interconnection Customer ___ others ____
Point of Interconnection:
Interconnection Customer's requested in-service date:
Section 2. Processing Fee or Deposit
If the Interconnection Request is submitted as Level 2, the nonrefundable processing fee payable to the utility is $500.
If the Interconnection Request is submitted as Level 3, the Interconnection Customer shall submit to the Utility the deposit is $1,000, or 50% of the estimated cost of the Feasibility Study, whichever is less.
Section 3. ] Small Generating Facility Information
Data apply only to the small generating facility, not the interconnection facilities.
Energy Source: ___ Solar ___ Wind ___ Hydro ___ Hydro Type
[ (e.g. Run-of-River) ]:_________
Diesel ___ Natural Gas ___ Fuel Oil ___ Other ([ state
type describe ]) ______________________________
Prime Mover: Fuel Cell__ Recip Engine__ Gas Turb__ Steam Turb__ Microturbine__ PV__ Other [ (describe) ]
Type of Generator: [ ____ ] Synchronous
____Induction ____ Inverter [ ]
Generator Nameplate Rating: ________kW [ (Typical) ]
Generator Nameplate kVAR: ______
Interconnection customer or customer-site load:
_________________kW [ (if none, so state) ]
Typical reactive load [ (if known) ]:
_________________
Maximum physical export capability requested: ______________ kW
List components of the small generating facility equipment package that are currently certified:
Equipment [ |
Certifying Entity |
1.________________ |
1.___________________ |
2.________________ |
2.___________________ |
3.________________ |
3.___________________ |
4.________________ |
4.___________________ |
5.________________ |
5.___________________ |
Is the prime mover compatible with the certified protective
relay package? [ ____]Yes ____No [ ____ ]
Generator (or solar collector)
Manufacturer, model name & number:_____________________________________
Version Number:_________________________________________
Nameplate Output Power Rating in kW: (Summer) _________ (Winter) ______
Nameplate Output Power Rating in kVA: (Summer) ________ (Winter) _______
Individual Generator Power Factor
Rated Power Factor: Leading: _____________Lagging: _______________
Total number of generators in wind farm to be interconnected pursuant to this
Interconnection Request: [ _______ ]
Elevation: ____ ___Single phase ___Three phase [ ____________ ]
Inverter manufacturer, model name & number [ (if
used) ]:___________________
List of adjustable set points for the protective equipment or software:_________
Note: A completed power systems load flow data sheet must be supplied with the Interconnection Request.
Small Generating Facility Characteristic Data (for inverter-based machines)
Max design fault contribution current:________
Instantaneous_____ or RMS [ ? ] _________
Harmonics characteristics: __________________________________________
Start-up requirements: _____________________________________________
Small Generating Facility Characteristic Data (for rotating machines)
RPM Frequency: _______________________________________________
[ (*) ] Neutral Grounding Resistor
(If Applicable): ____________
Synchronous Generators:
Direct Axis Synchronous Reactance, Xd: _______ P.U.
Direct Axis Transient Reactance, X'd: ___________ P.U.
Direct Axis Subtransient Reactance, X"d: ______________P.U.
Negative Sequence Reactance, X2: _________ P.U.
Zero Sequence Reactance, X0: ____________ P.U.
KVA Base: __________________________
Field Volts: ______________
Field Amperes: ______________
Induction Generators:
Motoring Power (kW): ______________
[ I2 2t I2t ] or
K (Heating Time Constant): ______________
Rotor Resistance, Rr: ______________
Stator Resistance, Rs: ______________
Stator Reactance, Xs: ______________
Rotor Reactance, Xr: ______________
Magnetizing Reactance, Xm: ______________
Short Circuit Reactance, Xd'': ______________
Exciting Current: ______________
Temperature Rise: ______________
Frame Size: ______________
Design Letter: ______________
Reactive Power Required In Vars (No Load): ______________
Reactive Power Required In Vars (Full Load): ______________
Total Rotating Inertia, H: _____________ Per Unit on kVA
[ Base base ]
Excitation and Governor System Data for Synchronous Generators Only
Provide appropriate IEEE model block diagram of excitation system, governor system and power system stabilizer (PSS) in accordance with the regional reliability council criteria. A PSS may be determined to be required by applicable studies. A copy of the manufacturer's block diagram may not be substituted.
[ Section 4. Customer's ] Interconnection Facilities Information
Will a transformer be used between the generator and the
point of [ common coupling interconnection ]
? [ ___ ] Yes ____No [ ____ ]
Will the transformer be provided by the interconnection
customer? [ ____ ] Yes ____No [ ____ ]
Transformer Data (If applicable, for interconnection customer-owned transformer):
Is the transformer: [ ____ ] single
phase _____three phase [ ? ___ ] Size:
[ ___________ ] kVA [ _____ ]
Transformer Impedance: _______% on __________kVA
[ Base base]
If Three Phase:
Transformer Primary:_____ Volts _____ Delta _____Wye _____ Wye Grounded
Transformer Secondary: _____Volts _____ Delta _____Wye _____ Wye Grounded
Transformer Tertiary:_____ Volts _____ Delta _____Wye _____ Wye Grounded
Transformer Fuse Data (If applicable, for interconnection customer-owned fuse):
(Attach copy of fuse manufacturer's minimum melt and total clearing time-current curves)
Manufacturer: ____________ Type: __________ Size: ______Speed: _______
Interconnecting Circuit Breaker (if applicable):
Manufacturer: ___________________ Type: __________
Load Rating (Amps): ______ Interrupting Rating (Amps): _______ Trip Speed (Cycles): ______
Interconnection Protective Relays (If Applicable):
If microprocessor-controlled:
Manufacturer: _________________________ Type: _____________________ Model No. ___________ Firmware ID: _____________ Instruction Book No. ______________
List of functions and adjustable setpoints for the protective equipment or software:
Setpoint Function |
Minimum |
Maximum |
1.________________ |
____________ |
__________ |
2.________________ |
____________ |
__________ |
3.________________ |
____________ |
__________ |
4.________________ |
____________ |
__________ |
5.________________ |
____________ |
__________ |
6.________________ |
____________ |
__________ |
If Discrete Components:
(Enclose copy of any proposed time-overcurrent coordination curves)
Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______
Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______
Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______
Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______
Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______
Current Transformer Data (If applicable):
(Enclose copy of manufacturer's excitation and ratio correction curves)
Manufacturer:____________________________________
Type: _______ Accuracy Class: ________Proposed Ratio Connection: ____
Manufacturer:____________________________________
Type: _______ Accuracy Class: ________Proposed Ratio Connection: ____
Potential Transformer Data (If applicable):
Manufacturer:____________________________________
Type: __________ Accuracy Class: _______Proposed Ratio Connection: ____
Manufacturer:____________________________________
Type: ________ Accuracy Class: _________Proposed Ratio Connection: ____
[ Section 5. ] General Information
Enclose [ a ] copy of [ the ]
site electrical one-line diagram showing the configuration of [ all
the ] small generating facility equipment, current and potential
circuits, and protection and control schemes.
Enclose [ a ] copy of any site
documentation that indicates the precise physical location of the proposed
[ small generating facility SGF ] (e.g.,
United States Geological Survey [ (USGS) ] topographic
map or other diagram or documentation).
[ Proposed Describe the proposed ]
location of [ the ] protective interface equipment
on [ the ] property [ (include address
if different from the interconnection customer's address) ] ________________________________________________
Enclose [ a ] copy of any site
documentation that describes and details the operation of the protection and
control schemes. Is available documentation enclosed? [ ___ ]
Yes ____No [ ____ ]
Enclose copies of schematic drawings for all protection and control circuits, relay current circuits, relay potential circuits, and alarm/monitoring circuits (if applicable).
Are schematic drawings enclosed? [ ___ ]
Yes ____No [ ____ ]
[ Applicant Section 6.
Interconnection Customer ] Signature
I hereby certify that, to the best of my knowledge, all the information provided in this Interconnection Request is true and correct.
[ For Interconnection Customer Signature ]
: _________________________ Date: ___________________________________
[ Section 7. Utility Acknowledgement of Receipt
Signed:
Title:
Utility:
Date:
Utility signature signifies only receipt of this form, in compliance with 20VAC5-314-50 of the State Corporation Commission's Regulations Governing Interconnection of Small Electrical Generators. ]
[ Schedule 5
LEVELS 2 AND 3 FACILITIES STUDY INFORMATION FORM FOR SMALL GENERATING FACILITIES LESS THAN 20 MW
1. Provide a location plan and simplified one-line diagram of the plant and station facilities. For staged projects, indicate future generation, future transmission circuits, and other major future facilities. On the one-line diagram, show (i) each generator, its electric connection configuration, and its generation capacity, (ii) the location and capacity of auxiliary power, and (iii) minimum load on CT/PT.
2. One set of metering is required for each generation connection to the new ring bus or existing utility station. Indicate the number of generation connections requiring a metering set: _____________________
3. Indicate whether an alternate source of auxiliary power will be available during CT/PT maintenance. Yes ___________ No ________________
4. Indicate whether a transfer bus on the generation side of the metering will require that each meter set be designed for the total plant generation. Indicate such on the one-line diagram. Yes ________ No _____
5. State the type of control system or Programmable Logic Controller (PLC) that will be located at the small generating facility.
__________________________________________________________________________________________________
6. State the protocol used by the control system or PLC. _____________________________________________________________________
7. Provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines.
8. State the physical dimensions of the proposed interconnection station.
________________________________________________________________________________________________________________
9. State the bus length from generation to interconnection station.
________________________________________________________________________________________________________________
10. Provide a diagram or description of the point of interconnection desired by the IC that is to be the point of interconnection in the system impact study report.
11. State the line length from interconnection station to utility system.
________________________________________________________________________________________________________________
12. State the pole or tower number observed in the field affixed to the pole or tower leg. _____________________________________________
13. State the number of third party easements required for distribution or transmission lines.
________________________________________________________________________________________________________________
14. Provide the following proposed schedule dates:
a. Date IC to begin construction: ______________________________________________
b. Date generator step-up transformers to receive back feed power: ______________________
c. Date IC will test SGF: ______________________________________________
d. Date IC will place SGF into commercial operation: _________________________________ ]
Schedule [ 5 6 ]
[ LEVEL 3 ] SMALL GENERATOR
INTERCONNECTION AGREEMENT (SGIA)
[ (For Small Generating Facilities Subject to the Level 3
Process) ]
This [ Small Generator ] Interconnection Agreement ("Agreement") is made and entered into this ______ day of ____________, 20__, by __________________
[ ("Distribution Company Utility ]"),
and _________________________________
("Interconnection Customer") each hereinafter sometimes referred to individually as "Party" or both referred to collectively as the "Parties."
[ Distribution Company Utility ]
Information
[ Distribution Company Utility ]:
_____________________________________________
Attention: ________________________________________________
Address: ________________________________________________________
[ City: ________________________ State:
________________ Zip: _________
City, State, Zip:___________________________________________ ]
Phone: _____________ Fax: _______________________
Interconnection Customer Information
Interconnection Customer: __________________________________________
Attention: ________________________________________________
Address: ________________________________________________
[ City: _________________________ State: _______________
Zip: _________
City, State, Zip:___________________________________________ ]
Phone: _______________________ Fax: _____________________________
Interconnection Customer Application No: _____________
In consideration of the mutual covenants set forth herein, the Parties agree as follows:
Article 1. Scope and Limitations of Agreement
1.1 This Agreement shall be used for all Interconnection
Requests submitted under the [ Small Generator Interconnection
Procedures (SGIP) Level 3 interconnections pursuant to the
Commission's Regulations Governing Interconnection of Small Electrical
Generators, Chapter 314 of the Virginia Administrative Code ].
1.2 This Agreement governs the terms and conditions under
which the Interconnection Customer's [ ("IC") ] Small
Generating Facility [ ("SGF") ] will
interconnect with, and operate in parallel with, the [ utility's
distribution utility ] system.
1.3 This Agreement does not constitute an agreement to
purchase or deliver the Interconnection Customer's power. The purchase or
delivery of power and other services [ , including station service
or backup power, ] that the [ Interconnection
Customer IC ] may require will be covered under separate
agreements [ , possibly with other parties ]. The
[ Interconnection Customer IC ] will be
responsible for separately making all necessary arrangements (including
scheduling) for delivery of electricity with the applicable [ Distribution
Company utility and provider of transmission service ].
1.4 Nothing in this Agreement is intended to affect any
other agreement between the [ Distribution Company
utility ] and the [ Interconnection Customer
IC ].
1.5 Responsibilities of the Parties
1.5.1 The Parties shall perform all obligations of this
Agreement in accordance with all applicable laws and regulations, operating
requirements, and Good [ Distribution Company Utility ]
Practice.
1.5.2 The [ Interconnection Customer
IC ] shall construct, interconnect, operate and maintain its
[ Small Generating Facility SGF ] and
construct, operate, and maintain its [ Customer's ] Interconnection
Facilities in accordance with the applicable manufacturer's recommended
maintenance schedule, in accordance with this Agreement, and with Good
[ Distribution Company Utility ] Practice.
1.5.3 The [ Distribution Company
utility ] shall construct, operate, and maintain its distribution
and transmission system and [ interconnection
attachment ] facilities in accordance with this Agreement, and with
Good [ Distribution Company Utility ] Practice.
1.5.4 The [ Interconnection Customer
IC ] agrees to construct its facilities [ or systems ]
in accordance with applicable specifications that meet or exceed those
provided by the National Electrical Safety Code, the American National
Standards Institute, IEEE, Underwriter's Laboratory, and operating requirements
in effect at the time of construction and other applicable national and state
codes and standards. The [ Interconnection Customer
IC ] agrees to design, install, maintain, and operate its
[ small generating facility SGF ] so as to
reasonably minimize the likelihood of a disturbance adversely affecting or
impairing the system or equipment of the [ Distribution Company
utility ] or affected systems [ and to otherwise
maintain and operate its SGF in accordance with the specifications and
certifications under which the SGF was initially installed and interconnected ].
1.5.5 Each Party shall operate, maintain, repair, and
inspect, and shall be fully responsible for the facilities that it now or
subsequently may own unless otherwise specified in the Attachments to this
Agreement. Each Party shall be responsible for the safe installation,
maintenance, repair and condition of their respective lines and appurtenances
on their respective sides of the point of change of ownership. The [ Distribution
Company utility ] and the [ Interconnection
Customer IC ], as appropriate, shall provide [ Interconnection
Attachment ] Facilities [ and Customer's
Interconnection Facilities ] that adequately protect the
[ Distribution Company's Transmission System, utility's ]
personnel, and other persons from damage and injury. The allocation of
responsibility for the design, installation, operation, maintenance and
ownership of [ Interconnection Attachment ] Facilities
[ and Customer's Interconnection Facilities ] shall be
delineated in the Attachments to this Agreement. [ The design,
installation, operation, and maintenance of such facilities shall be the
responsibility of the owner except as otherwise provided for in this Agreement. ]
1.5.6 The [ Distribution Company
utility ] shall coordinate with all affected systems to support the
interconnection.
1.6 Parallel operation obligations
Once the [ small generating facility
SGF ] has been authorized to commence parallel operation, the
[ Interconnection Customer IC ] shall abide
by all rules and procedures pertaining to the parallel operation of the
[ small generating facility SGF ] including,
but not limited to the rules and procedures concerning the operation of
generation set forth in the tariff.
1.7 Metering
The [ Interconnection Customer
IC ] shall be responsible for the [ Distribution
Company's utility's ] reasonable and necessary cost for
the purchase, installation, operation, maintenance, testing, repair, and
replacement of metering and data acquisition equipment specified in Attachments
2 and 3 of this Agreement. The [ Interconnection Customer's
IC's ] metering (and data acquisition, as required) equipment shall
conform to applicable industry rules and operating requirements.
1.8 Reactive power
1.8.1 The [ Interconnection Customer
IC ] shall design its [ small generating facility
SGF ] to maintain a composite power delivery at continuous rated
power output at the point of interconnection at a power factor within the range
of 0.95 leading to 0.95 lagging, unless the [ Distribution
Company utility ] has established different requirements
that apply to all similarly situated generators in the control area on a
comparable basis. The requirements of this paragraph shall not apply to wind
generators.
1.8.2 The [ Distribution Company
utility ] is required to pay the Interconnection Customer for
reactive power that the [ Interconnection Customer IC ]
provides or absorbs from the [ small generating facility
SGF ] when the [ Distribution Company
utility ] requests the [ Interconnection Customer
IC ] to operate its [ small generating facility
SGF ] outside the range specified in article 1.8.1. In addition, if
the [ Distribution Company utility ] pays
its own or affiliated generators for reactive power service within the
specified range, it must [ also similarly ] pay
the [ Interconnection Customer IC ].
1.8.3 Payments shall be in accordance with the [ Interconnection
Customer's IC's ] applicable rate schedule [ then
as may be ] in effect [ and accepted by the appropriate
government authority ]. To the extent that no rate schedule is in
effect at the time the Interconnection Customer is required to provide or
absorb reactive power under this Agreement, the [ Parties agree
to IC may ] expeditiously file such rate schedule
[ and agree with the appropriate government authority,
and the utility agrees ] to support any request for waiver of
[ the State Corporation Commission's any ] prior
notice requirement [ of such authority ] in order to
[ compensate permit compensation to ] the
[ Interconnection Customer IC ] from the time
service commenced.
1.9 Capitalized terms used herein shall have the meanings
specified in the [ Glossary of Terms definitions ]
in Attachment 1 to Schedule [ 5 6 ] or
[ in ] the body of this Agreement.
Article 2. Inspection, Testing, Authorization, and Right of Access
2.1 Equipment testing and inspection
2.1.1 The Interconnection Customer shall test and inspect
its small generating facility and interconnection facilities prior to
interconnection. The [ Interconnection Customer IC ]
shall notify the [ Distribution Company utility ]
of such activities no fewer than five business days (or as may be agreed to
by the Parties) prior to such testing and inspection. Testing and inspection
shall occur on a business day. The [ Distribution Company
utility ] may, at its own expense, send qualified personnel to the
[ small generating facility SGF ] site to
inspect the interconnection and observe the testing. The [ Interconnection
Customer IC ] shall provide the [ Distribution
Company utility ] a written test report when such
testing and inspection is completed.
2.1.2 The [ Distribution Company
utility ] shall provide the [ Interconnection
Customer IC ] written acknowledgment that it has
received the [ Interconnection Customer's IC's ]
written test report. Such written acknowledgment shall not be deemed to be
or construed as any representation, assurance, guarantee, or warranty by the
[ Distribution Company utility ] of the
safety, durability, suitability, or reliability of the [ small
generating facility SGF ] or any associated control,
protective, and safety devices owned or controlled by the [ Interconnection
Customer IC ] or the quality of power produced by the
[ small generating facility SGF ].
2.2 Authorization required prior to parallel operation
2.2.1 The [ Distribution Company
utility ] shall use reasonable efforts to list applicable parallel
operation requirements in Attachment 5 of this Agreement. Additionally, the
[ Distribution Company utility ] shall notify
the Interconnection Customer of any changes to these requirements as soon as
they are known. The [ Distribution Company utility ]
shall make reasonable efforts to cooperate with the [ Interconnection
Customer IC ] in meeting requirements necessary for the
[ Interconnection Customer IC ] to commence
parallel operations by the in-service date.
2.2.2 The [ Interconnection Customer
IC ] shall not operate its [ small generating
facility SGF ] in parallel with the [ Distribution
Company's utility's ] system without prior written
authorization of the [ Distribution Company utility].
The [ Distribution Company utility ] will
provide such authorization once the [ Distribution Company
utility ] receives notification that the [ Interconnection
Customer IC ] has complied with all applicable parallel
operation requirements. Such authorization shall not be unreasonably withheld,
conditioned, or delayed.
2.3 Right of access
2.3.1 Upon reasonable notice, the [ Distribution
Company utility ] may send a qualified person to the
premises of the Interconnection Customer at or immediately before the time the
[ small generating facility SGF ] first
produces energy to inspect the interconnection, and observe the commissioning
of the [ small generating facility SGF ] (including
any required testing), startup, and operation for a period of up to three
business days after initial start-up of the unit. In addition, the [ Interconnection
Customer IC ] shall notify the [ Distribution
Company utility ] at least five business days prior to conducting
any on-site verification testing of the [ small generating
facility SGF ].
2.3.2 Following the initial inspection process described
above, at reasonable hours, and upon reasonable notice, or at any time without
notice in the event of an emergency or hazardous condition, the [ Distribution
Company utility ] shall have access to the
Interconnection Customer's premises for any reasonable purpose in connection
with the performance of the obligations imposed on it by this Agreement or if
necessary to meet its legal obligation to provide service to its customers.
2.3.3 Each Party shall be responsible for its own costs
associated with [ following ] this article.
Article 3. Effective Date, Term, Termination, and Disconnection
3.1 Effective date
This Agreement shall become effective upon execution by
the Parties [ subject to acceptance by the State Corporation
Commission's Division of Energy Regulation (if applicable), or if filed
unexecuted, upon the date specified by the State Corporation Commission's Division
of Energy Regulation]. The [ Distribution Company
utility ] shall promptly file this Agreement with the [ State
Corporation ] Commission's Division of Energy Regulation upon
execution [ , if required ].
3.2 Term of Agreement
This Agreement [ shall become effective on
the effective date and ] shall remain in effect for a period of
10 years from the effective date or such other longer period as the
Interconnection Customer may request and shall be automatically renewed for
each successive one-year period thereafter, unless terminated earlier in
accordance with article 3.3 of this Agreement.
3.3 Termination
No termination shall become effective until the Parties
have complied with all applicable laws and regulations applicable to such
termination, including the filing with the [ State Corporation ]
Commission's Division of Energy Regulation of a notice of termination of
this Agreement [ (if required), which notice has been accepted
for filing by commission's Division of Energy Regulation ].
3.3.1 The Interconnection Customer may terminate this
Agreement at any time by giving the [ Distribution Company
utility ] 20 business days written notice.
3.3.2 Either Party may terminate this Agreement after default pursuant to article 7.6.
3.3.3 Upon termination of this Agreement, the [ small
generating facility Small Generating Facility ] will be
disconnected from the [ Distribution Company's
utility ] system. The termination of this Agreement shall not
relieve either Party of its liabilities and obligations, owed or continuing at
the time of the termination.
[ 3.3.4 This provisions of this article shall
survive termination or expiration of this Agreement. ]
3.4 Temporary disconnection
Temporary disconnection shall continue only for so long as
reasonably necessary under Good [ Distribution Company
Utility ] Practice.
3.4.1 Emergency Conditions -- "Emergency
Condition" shall mean a condition or situation: (i) that in the judgment
of the Party making the claim is imminently likely to endanger life or
property; or (ii) that, in the case of the [ Distribution
Company utility ], is imminently likely (as determined
in a non-discriminatory manner) to cause a material adverse effect on the
security of, or damage to the [ distribution utility ]
system, the [ Distribution Company's Interconnection
Attachment ] Facilities or the electrical facilities of others to
which the [ Distribution Company's distribution
utility ] system is directly connected; or (iii) that, in the case
of the Interconnection Customer, is imminently likely (as determined in a
non-discriminatory manner) to cause a material adverse effect on the security
of, or damage to, the [ small generating facility
Small Generating Facility ] or the [ Interconnection ]
Customer's [ interconnection facilities
Interconnection Facilities ]. Under emergency conditions, the
[ Distribution Company utility ] may
immediately suspend interconnection service and temporarily disconnect the
[ small generating facility SGF ]. The
[ Distribution Company utility ] shall notify
the [ Interconnection Customer IC ] promptly
when it becomes aware of an emergency condition that may reasonably be expected
to affect the [ Interconnection Customer's IC's ]
operation of the [ small generating facility SGF ].
The [ Interconnection Customer IC ] shall
notify the [ Distribution Company utility ] promptly
when it becomes aware of an emergency condition that may reasonably be expected
to affect the [ Distribution Company's utility ]
system or other affected systems. To the extent information is known, the notification
shall describe the emergency condition, the extent of the damage or deficiency,
the expected effect on the operation of both Parties' facilities and
operations, its anticipated duration, and the necessary corrective action.
3.4.2 Routine maintenance, construction, and repair
The [ Distribution Company
utility ] may interrupt interconnection service or curtail the
output of the [ small generating facility SGF ]
and temporarily disconnect the [ small generating facility
SGF ] from the [ Distribution Company's distribution
utility's ] system when necessary for routine maintenance,
construction, and repairs on the [ Distribution Company's
distribution utility ] system. The [ Distribution
Company utility ] shall provide the [ Interconnection
Customer IC ] with [ at least ] five
business days notice prior to such interruption [ unless
circumstances require shorter notice ]. The [ Distribution
Company utility ] shall use reasonable efforts to
coordinate such reduction or temporary disconnection with the [ Interconnection
Customer IC ].
3.4.3 Forced outages
During any forced outage, the [ Distribution
Company utility ] may suspend interconnection service to
effect immediate repairs on the [ Distribution Company's
distribution utility ] system. The [ Distribution
Company utility ] shall use reasonable efforts to
provide the [ Interconnection Customer IC ] with
prior notice. If prior notice is not given, the [ Distribution
Company utility ] shall, upon request, provide the
[ Interconnection Customer IC ] written
documentation after the fact explaining the circumstances of the disconnection.
3.4.4 Adverse operating effects
The [ Distribution Company
utility ] shall notify the [ Interconnection
Customer IC ] as soon as practicable if, based on Good
[ Distribution Company Utility ] Practice,
operation of the [ small generating facility SGF ]
may cause disruption or deterioration of service to other customers served
from the [ same electric utility ] system
[ or affected systems], or if operating the [ small
generating facility SGF ] could cause damage to the
[ Distribution Company's distribution utility ] system
or affected systems. Supporting documentation used to reach the decision to
disconnect shall be provided to the [ Interconnection Customer
IC ] upon request. If, after notice, the [ Interconnection
Customer IC ] fails to remedy the adverse operating
effect within a reasonable time, the [ Distribution Company
utility ] may disconnect the [ small generating
facility SGF ]. The [ Distribution
Company utility ] shall provide the [ Interconnection
Customer IC ] with a five business day notice of such
disconnection, unless the provisions of article 3.4.1 apply.
3.4.5 Modification of the [ small generating
facility Small Generating Facility ]
The Interconnection Customer must receive written
authorization from the [ Distribution Company utility ]
before making [ any change changes ] to
the [ small generating facility SGF or mode of
operations ] that may have a material impact on the safety or
reliability of the [ Distribution Company's utility ]
system [ or affected system ]. Such authorization
shall not be unreasonably withheld. Modifications shall be done in accordance
with Good [ Distribution Company Utility ] Practice.
If the [ Interconnection Customer IC ] makes
such [ modification modifications ] without
the [ Distribution Company's utility's ] prior
written authorization, the latter shall have the right to temporarily
disconnect the [ small generating facility SGF ].
3.4.6 Reconnection
The Parties shall cooperate with each other to restore the
[ small generating facility SGF ],
interconnection facilities, and the [ Distribution Company's
distribution utility ] system to their normal operating
state as soon as reasonably practicable following a temporary disconnection.
Article 4. Cost Responsibility for [ Customer's ] Interconnection Facilities [ , Attachment Facilities, ] and Distribution Upgrades
4.1 [ Customer's ] Interconnection
[ facilities Facilities ]
[ The IC shall be responsible for the costs associated with owning, operating, maintaining, repairing, and replacing the Customer's Interconnection Facilities. ]
[ 4.1.1 4.2 Attachment Facilities ]
The [ Interconnection Customer IC ]
shall pay for [ the cost of one-time and ongoing
costs of installing, owning, operating, maintaining and replacing ] the
[ interconnection attachment ] facilities
itemized in Attachment 2 of this Agreement. The [ Distribution
Company utility ] shall provide [ a best
estimate an estimated ] cost [ ,
including overheads, ] for the purchase and construction of
[ its interconnection the attachment ] facilities
and provide a detailed itemization of such costs. Costs associated with
[ interconnection attachment ] facilities may
be shared with other entities that may benefit from such facilities by
agreement of the [ Interconnection Customer IC ],
such other entities, and the [ Distribution Company
utility ].
[ 4.1.2 The Interconnection Customer shall be
responsible for its share of all reasonable expenses, including overheads,
associated with (i) owning, operating, maintaining, repairing, and replacing
its own interconnection facilities, and (ii) operating, maintaining, repairing,
and replacing the Distribution Company's interconnection facilities.
4.2 4.3 ]
Distribution upgrades
The [ Distribution
Company utility ] shall design, procure, construct,
install, and own the distribution upgrades described in Attachment 6 of this
Agreement. [ The actual cost of the distribution upgrades shall be
directly assigned to the IC. ] If the [ Distribution
Company utility ] and the [ Interconnection
Customer IC ] agree, the [ Interconnection
Customer IC ] may construct distribution upgrades that
are located on land owned by the [ Interconnection Customer
IC ]. [ The actual cost of the distribution
upgrades, including overheads, shall be directly assigned to the
Interconnection Customer. ]
[ Article 5. Cost Responsibility for System
Upgrades
5.1 Applicability
No portion of this article 5 shall apply unless the
interconnection of the small generating facility requires system upgrades.
5.2 System upgrades
The Distribution Company shall design, procure,
construct, install, and own the system upgrades described in Attachment 3 of
this Agreement. If the Distribution Company and the Interconnection Customer
agree, the Interconnection Customer may construct system upgrades that are
located on land owned by the Interconnection Customer. Unless the Distribution
Company elects to pay for system upgrades, the actual cost of the system
upgrades, including overheads, shall be borne initially by the Interconnection
Customer.
5.2.1 Repayment of amounts advanced for system upgrades
The Interconnection Customer shall be entitled to a cash
repayment, equal to the total amount paid to the Distribution Company and
affected system operator, if any, for system upgrades, including any tax
gross-up or other tax-related payments associated with the system upgrades, and
not otherwise refunded to the Interconnection Customer, to be paid to the
Interconnection Customer on a dollar-for-dollar basis for the nonusage
sensitive portion of transmission charges, as payments are made under the
Distribution Company's tariff and affected system's tariff for distribution
services with respect to the small generating facility. Upgrades through the date
on which the Interconnection Customer receives a repayment of such payment
pursuant to this subparagraph. The Interconnection Customer may assign such
repayment rights to any person.
5.2.1.1 Notwithstanding the foregoing, the
Interconnection Customer, the Distribution Company, and affected system
operator may adopt any alternative payment schedule that is mutually agreeable
so long as the Distribution Company and affected system operator take one of
the following actions no later than five years from the commercial operation
date: (i) return to the Interconnection Customer any amounts advanced for
system upgrades not previously repaid, or (ii) declare in writing that the
Distribution Company or affected system operator will continue to provide
payments to the Interconnection Customer on a dollar-for-dollar basis for the
nonusage sensitive portion of transmission charges, or develop an alternative
schedule that is mutually agreeable and provides for the return of all amounts
advanced for system upgrades not previously repaid; however, full reimbursement
shall not extend beyond 20 years from the commercial operation date.
5.2.1.2 If the small generating facility fails to
achieve commercial operation, but it or another generating facility is later
constructed and requires use of the system upgrades, the Distribution Company
and affected system operator shall at that time reimburse the Interconnection
Customer for the amounts advanced for the system upgrades. Before any such
reimbursement can occur, the Interconnection Customer, or the entity that
ultimately constructs the generating facility, if different, is responsible for
identifying the entity to which reimbursement must be made.
5.3 Special provisions for affected systems
Unless the Distribution Company provides, under this
Agreement, for the repayment of amounts advanced to affected system operator
for system upgrades, the Interconnection Customer and affected system operator
shall enter into an agreement that provides for such repayment. The agreement
shall specify the terms governing payments to be made by the Interconnection
Customer to affected system operator as well as the repayment by affected
system operator.
Article 5. Transmission System
5.1 Transmission system upgrades
5.1.1 No portion of section 5.1 of this article 5 shall apply unless the interconnection of the Small Generating Facility requires transmission system upgrades.
5.1.2 The utility shall design, procure, construct, install, and own the transmission system upgrades described in Attachment 6 of this Agreement. If the utility and the Interconnection Customer agree, the IC may construct transmission system upgrades that are located on land owned by the IC. The costs of the transmission system upgrades shall be borne by the IC.
5.1.3 Notwithstanding any other provision of section 5.1 of article 5, in the event and to the extent an RTE has rules, tariffs, agreements, or procedures properly applying to transmission system upgrades, the provisions of section 5.2 of article 5 shall apply to such upgrades.
5.2 Regional Transmission Entities
Notwithstanding any other provision of this Agreement, if the utility's transmission system is under the control of an RTE and the RTE has rules, tariffs, agreements or procedures properly governing operation of the SGF, transmission of the output of the SGF, sale of the output of the SGF, system upgrades required for interconnection of the SGF, or other aspects of the interconnection and operation of the SGF, the IC and the utility shall comply with the applicable of such agreements, rules, tariffs, or procedures. ]
[ 5.4 5.3 ] Rights under
other agreements
Notwithstanding any other provision of this Agreement,
nothing herein shall be construed as relinquishing or foreclosing any rights,
including but not limited to firm transmission rights, capacity rights,
transmission congestion rights, or transmission credits, that the [ Interconnection
Customer IC ] shall be entitled to, now or in the
future, under any other agreement or tariff as a result of, or otherwise associated
with system upgrades, including the right to obtain cash reimbursements or
transmission credits for transmission service that is not associated with the
[ small generating facility SGF ].
Article 6. Billing, Payment, Milestones, and Financial Security
6.1 Billing and payment procedures and final accounting
6.1.1 The [ Distribution Company
utility ] shall bill the [ Interconnection Customer
IC ] for the design, engineering, construction, and procurement
costs of [ interconnection attachment ] facilities
and upgrades contemplated by this Agreement on a monthly basis, or as otherwise
agreed by the Parties. The [ Interconnection Customer
IC ] shall pay each bill within 30 calendar days of receipt, or as
otherwise agreed to by the Parties.
6.1.2 Within [ three months 120
calendar days ] of completing the construction and installation of
the [ Distribution Company's interconnection
attachment ] facilities and/or [ distribution ]
upgrades described in the Attachments to this Agreement, the [ Distribution
Company utility ] shall provide the [ Interconnection
Customer IC ] with a final accounting report of any
difference between (i) the [ Interconnection Customer's
IC's ] cost responsibility for the actual cost of such facilities
or upgrades, and (ii) the [ Interconnection Customer's
IC's ] previous aggregate payments to the [ Distribution
Company utility ] for such facilities or upgrades. If
the [ Interconnection Customer's IC's ] cost
responsibility exceeds its previous aggregate payments, the [ Distribution
Company utility ] shall invoice the [ Interconnection
Customer IC ] for the amount due and the [ Interconnection
Customer IC ] shall make payment to the [ Distribution
Company utility ] within 30 calendar days. If the
[ Interconnection Customer's IC's ] previous
aggregate payments exceed its cost responsibility under this Agreement, the
[ Distribution Company utility ] shall refund
to the [ Interconnection Customer IC ] an
amount equal to the difference within 30 calendar days of the final accounting
report.
6.2 Milestones
The Parties shall agree on milestones for which each Party
is responsible and [ list them such milestone shall
be listed ] in Attachment 4 of this Agreement. A Party's
[ milestones ] obligations under this provision may be
[ extended modified ] by agreement. If a
Party anticipates that it will be unable to meet a milestone for any reason
other than a Force Majeure [ Event event], it shall
immediately [ (i) ] notify the other Party of the
reason(s) for not meeting the milestone [ , ] and
[ (i) (ii) ] propose the earliest reasonable
alternate date by which it can attain this and future milestones, and
[ (ii) requesting (iii) request ] appropriate
amendments to Attachment 4. The Party affected by the failure to meet a
milestone shall not [ unreasonably ] withhold
agreement to such an amendment unless it will suffer [ significant ]
uncompensated economic or operational harm from the delay, attainment of the
same milestone has previously been delayed, or it has reason to believe that
the delay in meeting the milestone is intentional or unwarranted
notwithstanding the circumstances explained by the Party proposing the
amendment.
6.3 Financial security arrangements
At least 20 business days prior to the commencement of the
design, procurement, installation, or construction of a discrete portion of the
[ Distribution Company's interconnection attachment ]
facilities and [ distribution ] upgrades, the
Interconnection Customer shall provide the [ Distribution
Company utility ], at the [ Interconnection
Customer's IC's ] option, a guarantee, a surety bond,
letter of credit or other form of security that is reasonably acceptable to the
[ Distribution Company utility ] and is
consistent with the Uniform Commercial Code of the jurisdiction where the point
of interconnection is located. Such security for payment shall be in an amount
sufficient to cover the costs for [ constructing, ]
designing, procuring, [ and ] installing
[ , and constructing ] the applicable portion of the
[ Distribution Company's interconnection attachment ]
facilities and [ distribution ] upgrades and shall
be reduced on a dollar-for-dollar basis for payments made to the [ Distribution
Company utility ] under this Agreement during its term.
In addition:
6.3.1 The guarantee must be made by an entity that meets
the creditworthiness requirements of the [ Distribution Company
utility ], and contain terms and conditions that guarantee payment
of any amount that may be due from the [ Interconnection
Customer IC ], up to an agreed-to maximum amount.
6.3.2 The letter of credit or surety bond must be issued by
a financial institution or insured reasonably acceptable to the [ Distribution
Company utility ] and must specify a reasonable
expiration date.
Article 7. Assignment, Liability, Indemnity, Force Majeure, Consequential Damages, and Default
7.1 Assignment
This Agreement may be assigned by either Party upon 15 business days prior written notice and opportunity to object by the other Party; provided that:
7.1.1 Either Party may assign this Agreement without the consent of the other Party to any affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this Agreement;
7.1.2 The Interconnection Customer shall have the right to
assign this Agreement, without the consent of the [ Distribution
Company utility ], for collateral security purposes to
aid in providing financing for the [ small generating facility
SGF ], provided that the [ Interconnection Customer
IC ] will promptly notify the [ Distribution Company
utility ] of any such assignment.
7.1.3 Any attempted assignment that violates this article is void and ineffective.
Assignment shall not relieve a Party of its obligations,
nor shall a Party's obligations be enlarged, in whole or in part, by reason
thereof. An assignee is responsible for meeting the same financial, credit, and
insurance obligations as the [ Interconnection Customer
IC ]. Where required, consent to assignment will not be
unreasonably withheld, conditioned or delayed.
7.2 Limitation of liability
Each Party's liability to the other Party for any loss, cost, claim, injury, liability, or expense, including reasonable attorney's fees, relating to or arising from any act or omission in its performance of this Agreement, shall be limited to the amount of direct damage actually incurred. In no event shall either Party be liable to the other Party for any indirect, special, consequential, or punitive damages, except as authorized by this Agreement.
7.3 Indemnity
7.3.1 This provision protects each Party from liability incurred to third parties as a result of carrying out the provisions of this Agreement. Liability under this provision is exempt from the general limitations on liability found in article 7.2.
7.3.2 The Parties shall at all times indemnify, defend, and hold the other Party harmless from, any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other Party's action or failure to meet its obligations under this Agreement on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnified Party.
7.3.3 If an indemnified [ person
Party ] is entitled to indemnification under this article as a
result of a claim by a third party, and the indemnifying Party fails, after
notice and reasonable opportunity to proceed under this article, to assume the
defense of such claim, such indemnified person may at the expense of the
indemnifying Party contest, settle or consent to the entry of any judgment with
respect to, or pay in full, such claim.
7.3.4 If an indemnifying [ party
Party ] is obligated to indemnify and hold any indemnified person
harmless under this article, the amount owing to the indemnified person shall
be the amount of such indemnified person's actual loss, net of any insurance or
other recovery.
7.3.5 Promptly after receipt by an indemnified person of
any claim or notice of the commencement of any action or administrative or
legal proceeding or small generator investigation as to which the indemnity
provided for in this article may apply, the indemnified person shall notify the
indemnifying [ party Party ] of such
fact. Any failure of or delay in such notification shall not affect a Party's
indemnification obligation unless such failure or delay is materially
prejudicial to the indemnifying party.
7.4 Consequential damages
Other than as expressly provided for in this Agreement, neither Party shall be liable under any provision of this Agreement for any losses, damages, costs or expenses for any special, indirect, incidental, consequential, or punitive damages, including but not limited to loss of profit or revenue, loss of the use of equipment, cost of capital, cost of temporary equipment or services, whether based in whole or in part in contract, in tort, including negligence, strict liability, or any other theory of liability; provided that damages for which a Party may be liable to the other Party under another agreement will not be considered to be special, indirect, incidental, or consequential damages hereunder.
7.5 Force Majeure
7.5.1 As used in this
article, a Force Majeure [ Event event ] means
"any act of God, labor disturbance, act of the public enemy, war,
insurrection, riot, fire, storm or flood, explosion, breakage or accident to
machinery or equipment, any order, regulation or restriction imposed by
governmental, military or lawfully established civilian authorities, or any
other cause beyond a Party's control. A Force Majeure [ Event
event ] does not include an act of negligence or intentional
wrongdoing."
7.5.2 If a Force Majeure [ Event
event ] prevents a Party from fulfilling any obligations under this
Agreement, the Party affected by the Force Majeure [ Event
event ] ([ " ] Affected Party
[ " ]) shall promptly notify the other Party,
either in writing or via the telephone, of the existence of the Force Majeure
[ Event event ]. The notification must
specify in reasonable detail the circumstances of the Force Majeure [ Event
event ], its expected duration, and the steps that the Affected
Party is taking to mitigate the effects of the event on its performance. The
Affected Party shall keep the other Party informed on a continuing basis of
developments relating to the Force Majeure [ Event
event ] until the event ends. The Affected Party will be entitled
to suspend or modify its performance of obligations under this Agreement (other
than the obligation to make payments) only to the extent that the effect of the
Force Majeure [ Event event ] cannot be
mitigated by the use of reasonable efforts. The Affected Party will use
reasonable efforts to resume its performance as soon as possible.
7.6 Default
7.6.1 No default shall exist where such failure to
discharge an obligation (other than the payment of money) is the result of a
Force Majeure [ Event event ] as defined
in this Small Generator Interconnection Agreement or the result of an act or
omission of the other Party. Upon a default, the [ nondefaulting
Nondefaulting ] Party shall give written notice of such default to
the [ defaulting Defaulting ] Party.
Except as provided in article 7.6.2, the [ defaulting
Defaulting ] Party shall have 60 calendar days from receipt of the
default notice within which to cure the default; however, if the default is not
capable of cure within 60 calendar days, the [ defaulting
Defaulting ] Party shall commence the cure within 20 calendar days
after notice and continuously and diligently complete the cure within six
months from receipt of the default notice; and, if cured within such time, the
default specified in such notice shall cease to exist.
7.6.2 If a default is not cured as provided in this
article, or if a default is not capable of being cured within the period
provided for herein, the [ nondefaulting
Nondefaulting ] Party shall have the right to terminate this
Agreement by written notice at any time until cure occurs, and be relieved of
any further obligation hereunder and, whether or not that Party terminates this
Agreement, to recover from the [ defaulting
Defaulting ] Party all amounts due hereunder, plus all other
damages and remedies to which it is entitled at law or in equity. The
provisions of this article will survive termination of this Agreement.
Article 8. Insurance
8.1 The Interconnection Customer shall, at its own
expense, maintain in force general liability insurance without any exclusion
for liabilities related to the interconnection undertaken pursuant to this
Agreement. The amount of such insurance shall be [ sufficient to
insure against all reasonably foreseeable direct liabilities given the size and
nature of the generating equipment being interconnected, the interconnection
itself, and the characteristics of the system to which the interconnection is
made in accordance with 20VAC5-314-160 of the Commission's
Regulations Governing the Interconnection of Small Electrical Generators ].
The [ Interconnection Customer IC ] shall
obtain additional insurance only if necessary as a function of owning and
operating a generating facility. Insurance shall be obtained from an insurance
provider authorized to do business in the State [ where the
interconnection is located of Virginia ]. Certification
that such insurance is in effect shall be provided upon request of the
[ Distribution Company utility ], except that
the [ Interconnection Customer IC ] shall
show proof of insurance to the [ Distribution Company
utility ] no later than 10 business days prior to the anticipated
commercial operation date [ of the SGF ]. An
[ Interconnection Customer IC ] of sufficient
creditworthiness may propose to self-insure for such liabilities, and such a
proposal shall not be unreasonably rejected.
8.2 The [ Distribution Company
utility ] agrees to maintain general liability insurance or self
insurance consistent with the [ Distribution Company's
utility's ] commercial practice. Such insurance or self-insurance
shall not exclude coverage for the [ Distribution Company's
utility's ] liabilities undertaken pursuant to this Agreement.
8.3 The Parties further agree to notify each other whenever an accident or incident occurs resulting in any injuries or damages that are included within the scope of coverage of such insurance, whether or not such coverage is sought.
Article 9. Confidentiality
9.1 Confidential information shall mean any confidential and/or proprietary information provided by one Party to the other Party that is clearly marked or otherwise designated "Confidential." For purposes of this Agreement all design, operating specifications, and metering data provided by the Interconnection Customer shall be deemed confidential information regardless of whether it is clearly marked or otherwise designated as such.
9.2 Confidential information does not include information previously in the public domain, required to be publicly submitted or divulged by governmental authorities (after notice to the other Party and after exhausting any opportunity to oppose such publication or release), or necessary to be divulged in an action to enforce this Agreement. Each Party receiving confidential information shall hold such information in confidence and shall not disclose it to any third party nor to the public without the prior written authorization from the Party providing that information, except to fulfill obligations under this Agreement, or to fulfill legal or regulatory requirements.
9.2.1 Each Party shall employ at least the same standard of care to protect confidential information obtained from the other Party as it employs to protect its own confidential information.
9.2.2 Each Party is entitled to equitable relief, by injunction or otherwise, to enforce its rights under this provision to prevent the release of confidential information without bond or proof of damages, and may seek other remedies available at law or in equity for breach of this provision.
[ 9.3 Notwithstanding anything in this Agreement to the contrary, if the Virginia State Corporation Commission ("Commission"), during the course of an investigation or otherwise, requests information from one of the Parties that is otherwise required to be maintained in confidence, the Party shall provide the requested information to the Commission, within the time provided for in the request for information. In providing the information to the Commission, the Party may request that the information be treated as confidential and nonpublic by the Commission and that the information be withheld from public disclosure. Parties are prohibited from notifying the other Party prior to the release of the confidential information to the Commission. ]
Article 10. Disputes
10.1 The Parties agree to attempt to resolve all disputes arising out of the interconnection process according to the provisions of this article.
10.2 In the event of a dispute, either Party shall provide the other Party with a written Notice of Dispute. Such Notice shall describe in detail the nature of the dispute. [ The Parties shall make a good faith effort to resolve the dispute informally within 10 business days. ]
10.3 If the dispute has not been resolved within
[ two 10 ] business days after receipt of the
Notice, either Party may [ contact seek resolution
assistance from ] the [ Commission's ] Division
of Energy Regulation [ for assistance in resolving the dispute
where the matter will be handled as an informal complaint. If that process is
unsatisfactory, either Party may petition the Commission to handle the dispute
as a formal complaint ].
[ Alternatively, either Party may seek resolution through the assistance of a dispute resolution service. The dispute resolution service will assist the Parties in either resolving the dispute or in selecting an appropriate dispute resolution venue (e.g., mediation, settlement judge, early neutral evaluation, or technical expert) to assist the Parties in resolving their dispute. Each Party agrees to conduct all negotiations in good faith and will be responsible for ˝ of any costs paid to neutral third parties. ]
10.4 [ Each Party agrees to conduct all
negotiations in good faith and will be responsible for one-half of any costs
paid to neutral third-parties If attempted dispute resolutions fail
to satisfy one or both of the Parties, then either Party may exercise whatever
rights and remedies it may have in equity or law consistent with the terms of
this Agreement ].
[ 10.5 If neither Party elects to seek assistance
from the State Corporation Commission's Division of Energy Regulation, or if
the attempted dispute resolution fails, then either Party may exercise whatever
rights and remedies it may have in equity or law consistent with the terms of
this Agreement. ]
Article 11. Taxes
11.1 The Parties agree to follow all applicable tax laws and regulations
11.2 Each Party shall cooperate with the other to maintain
the other Party's tax status. Nothing in this Agreement is intended to
adversely affect the [ Distribution Company's
utility's ] tax exempt status with respect to the issuance of bonds
including, but not limited to, local furnishing bonds.
Article 12. Miscellaneous
12.1 Governing [ Law, Regulatory Authority,
and Rules law, regulatory authority, and rules ]
The validity, interpretation and enforcement of this
Agreement and each of its provisions shall be governed by the laws of the
[ state State of ] Virginia without regard to
its conflicts of law principles. This Agreement is subject to all applicable
laws and regulations. Each Party expressly reserves the right to seek changes
in, appeal, or otherwise contest any laws, orders, or regulations of a
governmental authority.
12.2 Amendment
The Parties may amend this Agreement by a written instrument duly executed by both Parties.
12.3 No [ Third-Party Beneficiaries
third-party beneficiaries ]
This Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and where permitted, their assigns.
12.4 Waiver
12.4.1 The failure of a Party to this Agreement to insist, on any occasion, upon strict performance of any provision of this Agreement will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party.
12.4.2 Any waiver at any time by either Party of its rights
with respect to this Agreement shall not be deemed [ to be ]
a continuing waiver or a waiver with respect to any other failure to comply
with any other obligation, right, [ or ] duty of this
Agreement. Termination or default of this Agreement for any reason by
[ the ] Interconnection Customer shall not constitute a
waiver of the [ Interconnection Customer's IC's ]
legal rights to obtain an interconnection from the [ Distribution
Company utility ]. Any waiver of this Agreement shall,
if requested, be provided in writing.
12.5 Entire Agreement
This Agreement, including all Attachments, constitutes the entire agreement between the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between the Parties with respect to the subject matter of this Agreement. There are no other agreements, representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, either Party's compliance with its obligations under this Agreement.
12.6 Multiple [ Counterparts
counterparts ]
This Agreement may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument.
12.7 No [ Partnership
partnership ]
This Agreement shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership between the Parties or to impose any partnership obligation or partnership liability upon either Party. Neither Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, the other Party.
12.8 Severability
If any provision or portion of this Agreement shall for any reason be held or adjudged to be invalid or illegal or unenforceable by any court of competent jurisdiction or other governmental authority, (i) such portion or provision shall be deemed separate and independent, (ii) the Parties shall negotiate in good faith to restore insofar as practicable the benefits to each Party that were affected by such ruling, and (iii) the remainder of this Agreement shall remain in full force and effect.
12.9 Environmental [ Releases
releases ]
Each Party shall notify the other Party, first orally and
then in writing, of the release of any hazardous substances, any asbestos or
lead abatement activities, or any type of remediation activities related to the
[ small generating facility or Small Generating Facility, ]
the [ customer's ] interconnection facilities,
[ or attachment facilities, ] each of which may reasonably
be expected to affect the other Party. The notifying Party shall (i) provide
the notice as soon as practicable, provided such Party makes a good faith
effort to provide the notice no later than 24 hours after such Party becomes
aware of the occurrence, and (ii) promptly furnish to the other Party copies of
any publicly available reports filed with any governmental authorities
addressing such events.
12.10 Subcontractors
Nothing in this Agreement shall prevent a Party from utilizing the services of any subcontractor as it deems appropriate to perform its obligations under this Agreement; however, each Party shall require its subcontractors to comply with all applicable terms and conditions of this Agreement in providing such services and each Party shall remain primarily liable to the other Party for the performance of such subcontractor.
12.10.1 The creation of any subcontract relationship shall
not relieve the hiring Party of any of its obligations under this Agreement.
The hiring Party shall be fully responsible to the other Party for the acts or
omissions of any subcontractor the hiring Party hires as if no subcontract had
been made; however, in no event shall the [ Distribution Company
utility ] be liable for the actions or inactions of the [ Interconnection
Customer IC ] or its subcontractors with respect to
obligations of the [ Interconnection Customer IC ]
under this Agreement. Any applicable obligation imposed by this Agreement
upon the hiring Party shall be equally binding upon, and shall be construed as
having application to, any subcontractor of such Party.
12.10.2 The obligations under this article will not be limited in any way by any limitation of subcontractor's insurance.
12.11 Reservation of [ Rights
rights ]
The [ Distribution Company
utility ] shall have the right to make a unilateral filing with the
Commission to modify this Agreement with respect to any rates, terms and
conditions, charges, classifications of service, rule or regulation.
Article 13. Notices
13.1 General
Unless otherwise provided
in this Agreement, any written notice, demand, or request required or
authorized in connection with this Agreement ("Notice") shall be
deemed properly given if delivered in person, delivered by recognized national
[ currier courier ] service, or sent by first
class mail, postage prepaid, to the person specified below:
If to the Interconnection Customer:
Interconnection Customer: ___________________________________________
Attention: ________________________________________________
Address: ________________________________________________
[ City: ______________________________
State:_______________ Zip:_______
City, State, Zip: ]
Phone: __________________ Fax: _________________
If to the [ Distribution Company
Utility ]:
[ Distribution Company Utility ]:
_______________________________________________
Attention: ________________________________________________
Address:_________________________________________
[ City: ______________________________
State:_______________ Zip:_______
City, State, Zip: ]
Phone: _________________ Fax: ____________________
13.2 Billing and [ Payment
payment ]
Billings and payments shall be sent to the addresses set out below:
If to the Interconnection Customer:
Interconnection Customer: ___________________________________________
Attention: ________________________________________________
Address: ________________________________________________
[ City: ______________________________
State:_______________ Zip:_______
City, State, Zip: ]
If to the [ Distribution Company
Utility ]:
[ Distribution Company Utility ]:
_______________________________________________
Attention: ________________________________________________
Address:_________________________________________
[ City: ______________________________
State:_______________ Zip:_______
City, State, Zip: ]
13.3 Alternative [ Forms forms ]
of [ Notice notice ]
Any notice or request required or permitted to be given by either Party to the other and not required by this Agreement to be given in writing may be so given by telephone, facsimile or e-mail to the telephone numbers and email addresses set out below:
If to the Interconnection Customer:
Interconnection Customer: ___________________________________________
Attention: ________________________________________________
Address: ________________________________________________
[ City: ______________________________
State:_______________ Zip:_______
City, State, Zip: ]
Phone: ___________________ Fax: __________________
If to the [ Distribution Company
Utility ]:
[ Distribution Company Utility]:
_______________________________________________
Attention: ________________________________________________
Address:_________________________________________
[ City: ______________________________
State:_______________ Zip:_______
City, State, Zip: ]
Phone: __________________ Fax: ___________________
13.4 Designated [ Operating Representative
operating representative]
The Parties may also designate operating representatives to conduct the communications which may be necessary or convenient for the administration of this Agreement. This person will also serve as the point of contact with respect to operations and maintenance of the Party's facilities.
Interconnection Customer's Operating Representative:
Interconnection Customer: ___________________________________________
Attention: ________________________________________________
Address: ________________________________________________
[ City: ______________________________
State:_______________ Zip:_______
City, State, Zip: ]
Phone: __________________ Fax: ___________________
[ Distribution Company's Utility's ]
Operating Representative:
[ Distribution Company Utility ]:
_______________________________________________
Attention: ________________________________________________
Address:________________________________________
[ City: ______________________________
State:_______________ Zip:_______
City, State, Zip: ]
Phone: __________________ Fax: ___________________
13.5 Changes to the [ Notice Information
notice information ]
Either Party may change this information by giving five business days written notice prior to the effective date of the change.
Article 14. Signatures
IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by their respective duly authorized representatives.
For the [ Distribution Company
Utility ]
Name: ________________________________________________
Title: ________________________________________________
Date: ________________________________________________
For the Interconnection Customer
Name: ________________________________________________
Title: ________________________________________________
Date: ________________________________________________
Attachment 1 to
Schedule [ 5 6 ]
Glossary of Terms
[ " ] Affected system [ –
An " means an ] electric [ utility ]
system other than [ that of ] the [ Distribution
Company's transmission system utility ] that may be
affected by the proposed interconnection.
[ "Affected system operator" means an entity that operates an affected system or, if the affected system is under the operational control of an independent system operator or a Regional Transmission Entity, such independent entity. ]
[ " ] Applicable laws and regulations
[ – All " means all ] duly promulgated
applicable federal, state and local laws, regulations, rules, ordinances,
codes, decrees, judgments, directives, or judicial or administrative orders,
permits and other duly authorized actions of any governmental authority.
[ "Attachment facilities" means the facilities and equipment owned, operated, and maintained by the utility that are built new in order to physically connect the customer’s interconnection facilities to the utility system. Attachment facilities shall not include distribution upgrades or previously existing distribution and transmission facilities. ]
[ " ] Business Day [ – "
means ] Monday through Friday, excluding federal holidays.
[ "Certified" has the meaning ascribed to it in Schedule 2 of Chapter 314 ( 20VAC5-314-10 et seq.) of the Virginia Administrative Code.
"Customer’s interconnection facilities" means all the facilities and equipment owned, operated and maintained by the Interconnection Customer, between the Small Generating Facility and the point of interconnection necessary to physically and electrically interconnect the Small Generating Facility to the utility system.
"Commission" means the Virginia State Corporation Commission. ]
[ " ] Default [ – The
" means the ] failure of a breaching Party to cure its breach
under the Small Generator Interconnection Agreement.
[ Distribution Company – The Utility that owns
and/or operates the Distribution System located in Virginia to which the small
generation facility proposes to interconnect its small generating facility. ]
[ " ] Distribution system [ –
The Distribution Company's " means the utility's ] facilities
and equipment [ used to transmit generally delivering ]
electricity to ultimate [ usage points such as homes and
industries directly from nearby generators or from interchanges with higher
voltage transmission systems which transport bulk power over longer distances.
The voltage levels at which distribution systems operate differ among areas
customers from substations supplied by higher voltages (usually at transmission
level). For purposes of this Agreement, all portions of the utility's
transmission system regulated by the Commission for which interconnections are
not within Federal Energy Regulatory Commission jurisdiction are considered
also to be subject to Commission regulations. ]
[ " ] Distribution upgrades
[ – The " means the ] additions,
modifications, and upgrades to the [ Distribution Company's
utility's ] distribution system at or beyond the point of
interconnection [ necessary ] to [ facilitate
abate problems on the utility's distribution system caused by the ] interconnection
of the [ small generating facility and render the transmission
service necessary to effect the Interconnection Customer's wholesale sale of
electricity in interstate commerce Small Generating Facility ].
Distribution upgrades do not include [ customer's ] interconnection
facilities [ or attachment facilities ].
[ "Energy service provider" means any entity supplying electric energy service to the Interconnection Customer.
"Facilities study" has the meaning ascribed to it in the commission’s regulations governing the interconnection of small generating facilities at 20VAC5-314-70 F.
"Feasibility study" has the meaning ascribed to it in the commission’s regulations governing the interconnection of small generating facilities at 20VAC5-314-70 D.
"FERC" means the Federal Energy Regulatory Commission.]
[ " ] Good [ Distribution
Company Utility ] Practice [ – Any
" means any ] of the practices, methods and acts engaged in or
approved by a significant portion of the electric industry during the relevant
time period, or any of the practices, methods and acts which, in the exercise
of reasonable judgment in light of the facts known at the time the decision was
made, could have been expected to accomplish the desired result at a reasonable
cost consistent with good business practices, reliability, safety and
expedition. Good [ Distribution Company Utility ]
Practice is not intended to be limited to the optimum practice, method, or
act to the exclusion of all others, but rather to be acceptable practices,
methods, or acts generally accepted in the region.
[ " ] Governmental authority
[ – Any " means any ] federal, state,
local or other governmental regulatory or administrative agency, court,
commission, department, board, or other governmental subdivision, legislature,
rulemaking board, tribunal, or other governmental authority having jurisdiction
over the Parties, their respective facilities, or the respective services they
provide, and exercising or entitled to exercise any administrative, executive,
police, or taxing authority or power; provided that such term does not include
the Interconnection Customer, the [ interconnection provider, or
any Affiliate thereof utility, or a utility affiliate ].
[ " ] Interconnection Customer
[ – Any " or "IC" means any ] entity
[ , including the Distribution Company, the transmission owner or
any of the affiliates or subsidiaries of either, that proposes to interconnect
its small generating facility with the Distribution Company's transmission
proposing to interconnect a new Small Generating Facility with the utility ]
system.
[ Interconnection facilities – The Distribution
Company's interconnection facilities and the Interconnection Customer's
interconnection facilities. Collectively, interconnection facilities include
all facilities and equipment between the small generating facility and the
point of interconnection, including any modification, additions or upgrades
that are necessary to physically and electrically interconnect the small
generating facility to the Distribution Company's transmission system.
Interconnection facilities are sole use facilities and shall not include
distribution upgrades or system upgrades.
" ] Interconnection request [ –
The Interconnection Customer's " means the IC's ] request,
in accordance with the tariff, to interconnect a new [ small
generating facility Small General Facility ], or to
increase the capacity of, or make a material modification to the operating
characteristics of, an existing [ small generating facility
Small Generating Facility ] that is interconnected with the
[ Distribution Company's utility ] system.
[ "Interconnection studies" means the studies conducted by the utility, or a third party agreed to by the utility and the Interconnection Customer, in order to determine the interaction of the Small Generating Facility with the utility system and the affected systems in order to specify any modifications to the Small Generating Facility or the electric systems studied to ensure safe and reliable operation of the Small Generating Facility in parallel with the utility system.
" ] Material modification [ –
A " means a ] modification that has a material
impact on the cost or timing of any Interconnection Request with a later queue
priority date.
[ System upgrades – Additions, modifications, and
upgrades to the Distribution Company's distribution and transmission system
required at or beyond the point at which the small generating facility
interconnects with the system to accommodate the interconnection of the small
generating facility with the Distribution Company's transmission system.
" ] Operating requirements [ –
Any " means any ] operating and technical
requirements that may be applicable due to [ Regional
Transmission Organization, Independent System Operator regional
transmission entity, independent system operator], control area, or the
[ Distribution Company's utility's ] requirements,
including those set forth in the Small Generator Interconnection Agreement.
[ " ] Party [ " ]
or [ " ] Parties [ " ]
[ – The Distribution Company means the utility ],
[ the ] Interconnection Customer or [ any
combination of the above both ].
[ " ] Point of interconnection
[ – The " means the ] point where the
[ customer's ] interconnection facilities connect
[ with to ] the [ Distribution
Company's transmission utility ] system.
[ Reasonable efforts – With respect to an action
required to be attempted or taken by a Party under the Small Generator
Interconnection Agreement, efforts that are timely and consistent with Good Distribution
Company Practice and are otherwise substantially equivalent to those a Party
would use to protect its own interests.
"Regional Transmission Entity" or "RTE" shall refer to an entity having the management and control of a utility’s transmission system as further set forth in § 56-579 of the Code of Virginia.
" ] Small Generating Facility [ –
The " or "generator" or "SGF" means the ]
Interconnection Customer's [ device equipment ]
for the production of electricity identified in the Interconnection Request
[ , but shall not include the Interconnection Customer's
interconnection facilities ].
[ "Small Generator Interconnection Agreement" or "SGIA" means the agreement between the utility and the Interconnection Customer as set forth in Schedule 6 of 20VAC5-314-170 of the Commission’s regulations governing interconnection of small electrical generators.
"Supplemental review" has the meaning ascribed to it in the Commission’s regulations governing the interconnection of small generating facilities at 20VAC5-314-70 E.
"System" or "utility system" means the distribution and transmission facilities owned, controlled, or operated by the utility that are used to deliver electricity.
"System impact study" has the meaning ascribed to it in the Commission’s regulations governing the interconnection of small generating facilities at 20VAC5-314-70 E. ]
[ " ] Tariff [ – The
" means the ] rates, terms and conditions filed by the utility
with the [ State Corporation ] Commission for
the purpose of providing [ commission-regulated
Commission-regulated ] electric service to retail customers.
[ Upgrades – The required additions and
modifications to the Distribution Company's distribution or transmission system
at or beyond the point of interconnection. Upgrades do not include
interconnection facilities.
"Transmission system" means the utility’s facilities and equipment delivering electric energy to the distribution system, such facilities usually being operated at voltages above the utility’s typical distribution system voltages.
"Utility" means the public utility company subject to regulation by the Commission pursuant to Chapter 10 (§ 56-232 et seq.) of Title 56 of the Code of Virginia with regard to rates and/or service quality to which the Interconnection Customer proposes to interconnect a Small Generating Facility. ]
Attachment 2 to
Schedule [ 5 6 ]
Description and Costs of the Small Generating Facility, [ Customer's ] Interconnection Facilities, [ Attachment Facilities ] and Metering Equipment
[ Equipment, including the small generating
facility, interconnection facilities, and metering equipment shall be itemized
and identified as being The following shall be provided in this
exhibit:
1. An itemization of the major equipment components ]
owned by the Interconnection Customer [ or and ]
the [ Distribution Company. The Distribution Company will
provide a best estimate itemized cost, including overheads, of its
interconnection facilities and metering equipment, and a best estimate itemized
cost of the annual operation and maintenance expenses associated with its
interconnection facilities and metering equipment utility, including
components of the Small Generating Facility, the customer’s interconnection
facilities, attachment facilities, and metering equipment. Such itemization
shall identify the owner of each item listed.
2. The utility’s estimated itemized cost of its attachment facilities and its metering equipment.
3. The utility’s estimated cost of its annual operation and maintenance expenses associated with attachment facilities and metering equipment to be charged to the Interconnection Customer ].
Attachment 3 to
Schedule [ 5 6 ]
[ [ Diagram to be provided by applicant ]
]
One-line Diagram Depicting the Small Generating Facility, [ Customer's ] Interconnection Facilities, [ Attachment Facilities, ] Metering Equipment, and [ Distribution ] Upgrades
[ (Diagram and description to be provided by Interconnection Customer) ]
Attachment 4 to
Schedule [ 5 6 ]
Milestones
In-Service Date: ___________________
Critical milestones and responsibility as agreed to by the Parties:
Milestone/Date |
Responsible Party |
(1)____________________ |
____________________ |
(2)____________________ |
____________________ |
(3)____________________ |
____________________ |
(4)____________________ |
____________________ |
(5)____________________ |
____________________ |
(6)____________________ |
____________________ |
(7)____________________ |
____________________ |
(8)____________________ |
____________________ |
(9)____________________ |
____________________ |
(10)___________________ |
____________________ |
Agreed to by:
For the [ Distribution Company
Utility ] ____________________ Date__________
For the Transmission Owner (If Applicable)_____________ Date__________
For the Interconnection Customer_____________________ Date___________
Attachment 5 to
Schedule [ 5 6 ]
Additional Operating Requirements for the [ Distribution
Company's Utility ] System and Affected Systems Needed
to Support the Interconnection Customer's Needs
The [ Distribution Company utility ]
shall [ also ] provide requirements that must
be met by the Interconnection Customer prior to initiating parallel operation
with the [ Distribution Company's utility ] system.
Attachment 6 to
Schedule [ 5 6 ]
[ Distribution Company's Utility's ]
Description of its [ Distribution and Transmission ] Upgrades
[ And Best and ] Estimate of Upgrade
Costs
The [ Distribution Company shall describe
upgrades and provide an itemized estimate of the cost, including overheads, of
the upgrades and annual operation and maintenance expenses associated with such
upgrades. The Distribution Company shall functionalize upgrade costs and annual
expenses as either transmission or distribution related. utility
shall provide the following in this attachment:
1. An itemized list of the upgrades required to be constructed by the utility prior to interconnection of the Small Generating Facility, with transmission and distribution related upgrades shown separately.
2. An estimate of the cost of each item listed pursuant to item 1.
3. An estimate of annual operation and maintenance expenses associated with such upgrades that are to be charged to the Interconnection Customer, shown separately for transmission and distribution related items. ]
Attestation
VA.R. Doc. No. R08-1147; Filed December 1, 2008, 10:48 a.m.