TITLE 20. PUBLIC UTILITIES AND TELECOMMUNICATIONS
REGISTRAR'S NOTICE: The
State Corporation Commission is claiming an exemption from the Administrative
Process Act in accordance with § 2.2-4002 A 2 of the Code of Virginia,
which exempts courts, any agency of the Supreme Court, and any agency that by
the Constitution is expressly granted any of the powers of a court of record.
Title of Regulation: 20VAC5-315. Regulations
Governing Net Energy Metering (amending 20VAC5-315-10 through 20VAC5-315-40;
adding 20VAC5-315-75).
Statutory Authority: §§ 12.1-13 and 56-594 of the
Code of Virginia.
Public Hearing Information: A public hearing will be
held upon request.
Public Comment Deadline: October 31, 2017.
Agency Contact: Armando deLeon, Utilities Engineer,
Division of Public Utility Regulation, State Corporation Commission, P.O. Box
1197, Richmond, VA 23218, telephone (804) 371-9392, FAX (804) 371-9350, or
email armando.deleon@scc.virginia.gov.
Summary:
Pursuant to Chapters 565 and 581 of the 2017 Acts of
Assembly, the proposed amendments (i) add a definition of small agricultural
generator and provide for the interconnection of small agricultural generators
to utilities because, as of July 1, 2019, agricultural customer-generators may
no longer interconnect with electric cooperatives but must do so as small
agricultural generators under § 56-594.2 of the Code of Virginia.
AT RICHMOND, AUGUST 25, 2017
COMMONWEALTH OF VIRGINIA, ex
rel.
STATE CORPORATION COMMISSION
CASE NO. PUR-2017-00099
Ex Parte: In the matter of amending regulations
governing net energy metering
ORDER ESTABLISHING PROCEEDING
The Regulations Governing Net Energy Metering, 20VAC5-315-10
et seq. ("Net Energy Metering Rules"), adopted by the State
Corporation Commission ("Commission") pursuant to § 56-594 of
the Virginia Electric Utility Regulation Act, Chapter 23
(§ 56-576 et seq.) of Title 56 of the Code of Virginia
("Code"), establish the requirements for participation by an eligible
customer-generator in net energy metering in the Commonwealth of Virginia. The
Net Energy Metering Rules include conditions for interconnection and metering,
billing, and contract requirements between net metering customers, electric
distribution companies, and energy service providers.
Chapters 565 and 581 of the 2017 Acts of Assembly
("Chapters 565 and 581") amended § 56-594 of the Code by adding a new
§ 56-594.2 to add a definition of "small agricultural generator"
and to provide for the interconnection of such generator to utilities. In
addition, Chapters 565 and 581 provide that on and after July 1, 2019,
interconnection of eligible agricultural customer-generators under § 56-594
shall cease for electric cooperatives only, and such facilities shall
interconnect solely as small agricultural generators under § 56-594.2. The
current Net Energy Metering Rules thus must be revised to reflect the changes
set forth in Chapters 565 and 581.
NOW THE COMMISSION, upon consideration of the matter, is of
the opinion and finds that a proceeding should be established to amend the Net
Energy Metering Rules to provide for the interconnection of small agricultural
generators, as defined in the Code.
To initiate this proceeding, the Commission Staff has
prepared proposed rules ("Proposed Rules") which are appended to this
Order. We will direct that notice of the Proposed Rules be given to the public
and that interested persons be provided an opportunity to file written comments
on, propose modifications or supplements to, or request a hearing on the
Proposed Rules. We will further direct that each Virginia electric
distribution company within the meaning of 20VAC5-315-20 serve a copy of this
Order upon each of their respective net metering customers and file a
certificate of service. Individuals should be specific in their comments,
proposals, or supplements to the Proposed Rules and address only those issues
pertaining to the amendment of § 56-594 of the Code of Virginia pursuant
to Chapters 565 and 581. Issues outside the scope of implementing these
amendments will not be open for consideration.
Accordingly, IT IS ORDERED THAT:
(1) This case is docketed and assigned Case No.
PUR-2017-00099.
(2) The Commission's Division of Information Resources shall
forward a copy of this Order to the Registrar of Regulations for publication in
the Virginia Register of Regulations.
(3) On or before September 19, 2017, each Virginia electric
distribution company shall serve a copy of this Order upon each of their
respective net metering customers and file with the Commission a certificate of
service no later than October 3, 2017, consistent with the findings above.
(4) On or before October 31, 2017, any interested person may
comment on, propose modifications or supplements to, or request a hearing on
the Proposed Rules by filing an original and fifteen (15) copies of such
comments or requests with Joel H. Peck, Clerk, State Corporation Commission,
c/o Document Control Center, P.O. Box 2118, Richmond, Virginia 23218.
Interested persons desiring to submit comments or hearing requests
electronically may do so by following the instructions available at the
Commission's website: http://www.scc.virginia.gov/case.
Individuals shall be specific in their comments, proposals, or supplements to
the Proposed Rules and shall address only those issues pertaining to the
amendment of § 56-594 of the Code of Virginia pursuant to Chapters 565 and
581. Issues outside the scope of implementing this amendment will not be open
for consideration. Any request for hearing shall state with specificity
why the issues raised in the request for hearing cannot be adequately addressed
in written comments. If a sufficient request for hearing is not received, the
Commission may consider the matter and enter an order based upon the papers
filed herein. Interested parties shall refer in their comments or requests to
Case No. PUR-2017-00099.
(5) This matter is continued.
AN ATTESTED COPY hereof shall be sent by the Clerk of the
Commission to all persons on the official Service List in this matter. The
Service List is available from the Clerk of the State Corporation Commission,
c/o Document Control Center, 1300 East Main Street, First Floor, Tyler
Building, Richmond, Virginia 23219.
20VAC5-315-10. Applicability and scope.
These regulations are promulgated pursuant to the provisions
of §§ 56-594 and 56-594.2 of the Virginia Electric Utility
Regulation Act (§ 56-576 et seq. of the Code of Virginia). They establish
requirements intended to facilitate net energy metering for customers owning
and operating, or contracting with persons to own or operate, or both,
electrical generators that use specific types of renewable energy as the total
fuel source. These regulations will standardize the interconnection requirements
for such facilities and will govern the metering, billing, payment and contract
requirements between net metering customers, electric distribution companies
and energy service providers. Agricultural net metering customers are subject
to the same provisions as nonagricultural net metering customers unless
otherwise specified. On or after July 1, 2019, interconnection of eligible
agricultural customer-generators shall cease for member-owned electric
cooperatives only, and such facilities shall interconnect solely as small
agricultural generators. For member-owned electric cooperatives, agricultural
net metering customers whose agricultural renewable fuel generators were
interconnected before July 1, 2019, may continue to participate in net energy metering
for a period not to exceed 25 years from the date of their agricultural
renewable fuel generator's original interconnection.
The amendments regarding agricultural net metering apply
to customers of investor-owned electric utilities on July 1, 2014, and apply to
customers of electric cooperatives on July 1, 2015, as provided in the State
Corporation Commission's Order Adopting Regulations, Case No. PUE-2014-00003,
dated June 23, 2014, and published in the Virginia Register of Regulations,
Volume 30, Issue 23, July 14, 2014.
These regulations also establish requirements for the
interconnection of small agricultural generators. Small agricultural generators
or agricultural renewable fuel generators may elect to interconnect as a net
metering customer or as small agricultural generators pursuant to
20VAC5-315-75, but not both. Existing eligible agricultural renewable fuel
generators may elect to become small agricultural generators, but may not
revert to being an agricultural renewable fuel generator after such election.
20VAC5-315-20. Definitions.
The following words and terms when used in this chapter shall
have the following meanings unless the context clearly indicates otherwise:
"Agricultural business" means any sole
proprietorship, corporation, partnership, electing small business (Subchapter
S) corporation, or limited liability company engaged primarily in the
production and sale of plants and animals, products collected from plants and
animals, or plant and animal services that are useful to the public.
"Agricultural net metering customer" means a
customer that operates an electrical generating facility consisting of one or
more agricultural renewable fuel generators having an aggregate generation
capacity of not more than 500 kilowatts as part of an agricultural business
under a net metering service arrangement. An agricultural net metering customer
may be served by multiple meters of one utility that are located at separate
but contiguous sites and that may be aggregated into one account. This account
shall be served under the appropriate tariff.
"Agricultural renewable fuel generator" or
"agricultural renewable fuel generating facility" means one or more
electrical generators that:
1. Use as their sole energy source solar power, wind power, or
aerobic or anaerobic digester gas;
2. The agricultural net metering customer owns and operates,
or has contracted with other persons to own or operate, or both;
3. Are located on land owned or controlled by the agricultural
business;
4. Are connected to the agricultural net metering customer's
wiring on the agricultural net metering customer's side of the agricultural net
metering customer's interconnection with the distributor;
5. Are interconnected and operated in parallel with an
electric company's distribution facilities; and
6. Are used primarily to provide energy to metered accounts of
the agricultural business.
"Billing period" means, as to a particular
agricultural net metering customer or a net metering customer, the time period
between the two meter readings upon which the electric distribution company and
the energy service provider calculate the agricultural net metering customer's
or net metering customer's bills.
"Billing period credit" means, for a nontime-of-use
agricultural net metering customer or a nontime-of-use net metering customer,
the quantity of electricity generated and fed back into the electric grid by
the agricultural net metering customer's agricultural renewable fuel generator
or generators or by the net metering customer's renewable fuel generator or
generators in excess of the electricity supplied to the customer over the
billing period. For time-of-use agricultural net metering customers or
time-of-use net metering customers, billing period credits are determined
separately for each time-of-use tier.
"Contiguous sites" means a group of land parcels in
which each parcel shares at least one boundary point with at least one other
parcel in the group. Property whose surface is divided only by public
right-of-way is considered contiguous.
"Customer" means a net metering customer or an
agricultural net metering customer.
"Demand charge-based time-of-use tariff" means a
retail tariff for electric supply service that has two or more time-of-use
tiers for energy-based charges and an electricity supply demand (kilowatt)
charge.
"Electric distribution company" means the entity
that owns and/or or operates the distribution facilities
delivering electricity to the premises of an agricultural net metering customer
or a net metering customer.
"Energy service provider (supplier)" means the
entity providing electricity supply service, either tariffed or competitive
service, to an agricultural net metering customer or a net metering customer.
"Excess generation" means the amount of electrical
energy generated in excess of the electrical energy consumed by the
agricultural net metering customer or net metering customer over the course of
the net metering period. For time-of-use agricultural net metering customers or
net metering customers, excess generation is determined separately for each
time-of-use tier.
"Generator" or "generating facility"
means an electrical generating facility consisting of one or more renewable
fuel generators or one or more agricultural renewable fuel generators that meet
the criteria under the definition of "net metering customer" and
"agricultural net metering customer," respectively.
"Net metering customer" means a customer owning and
operating, or contracting with other persons to own or operate, or both, an
electrical generating facility consisting of one or more renewable fuel
generators having an aggregate generation capacity of not more than 20
kilowatts for residential customers and not more than one megawatt for
nonresidential customers. The generating facility shall be operated under a net
metering service arrangement.
"Net metering period" means each successive
12-month period beginning with the first meter reading date following the final
interconnection of an agricultural net metering customer or a net metering customer's
generating facility consisting of one or more agricultural renewable fuel
generators or one or more renewable fuel generators, respectively, with the
electric distribution company's distribution facilities.
"Net metering service" means providing retail
electric service to an agricultural net metering customer operating an
agricultural renewable fuel generating facility or a net metering customer
operating a renewable fuel generating facility and measuring the difference,
over the net metering period, between the electricity supplied to the customer
from the electric grid and the electricity generated and fed back to the
electric grid by the customer.
"Person" means any individual, sole proprietorship,
corporation, limited liability company, partnership, association, company,
business, trust, joint venture, or other private legal entity, the
Commonwealth, or any city, county, town, authority, or other political
subdivision of the Commonwealth.
"Renewable Energy Certificate" or "REC"
represents the renewable energy attributes associated with the production of
one megawatt-hour (MWh) of electrical energy by a generator.
"Renewable fuel generator" or "renewable fuel
generating facility" means one or more electrical generators that:
1. Use renewable energy, as defined by § 56-576 of the
Code of Virginia, as their total fuel source;
2. The net metering customer owns and operates, or has
contracted with other persons to own or operate, or both;
3. Are located on the net metering customer's premises and connected
to the net metering customer's wiring on the net metering customer's side of
its interconnection with the distributor;
4. Are interconnected pursuant to a net metering arrangement
and operated in parallel with the electric distribution company's distribution
facilities; and
5. Are intended primarily to offset all or part of the net
metering customer's own electricity requirements. The capacity of any
generating facility installed on or after July 1, 2015, shall not exceed the
expected annual energy consumption based on the previous 12 months of billing
history or an annualized calculation of billing history if 12 months of billing
history is not available.
"Small agricultural generating facility" means
an electrical generating facility that:
1. Has a capacity of not more than 1.5 megawatts and does
not exceed 150% of the customer's expected annual energy consumption based on
the previous 12 months of billing history or an annualized calculation of
billing history if 12 months of billing history is not available;
2. Uses as its total source of fuel renewable energy;
3. Is located on the customer's premises and is
interconnected with the utility's distribution system through a separate meter;
4. Is interconnected and operated in parallel with an
electric utility's distribution system but not transmission facilities;
5. Is designed so that the electricity generated is
expected to remain on the utility's distribution system; and
6. Is a qualifying small power production facility pursuant
to the Public Utility Regulatory Policies Act of 1978 (P.L. 95-617).
"Small agricultural generator" means a customer
that:
1. Is not an eligible agricultural customer-generator
pursuant to § 56-594 of the Code of Virginia;
2. Operates a small agricultural generating facility as
part of an agricultural business;
3. May be served by multiple meters that are located at
separate but contiguous sites;
4. May aggregate the electricity consumption measured by
the meters, solely for purposes of calculating 150% of the customer's expected
annual energy consumption but not for billing or retail service purposes,
provided that the same utility serves all of its meters;
5. Uses not more than 25% of the contiguous land owned or
controlled by the agricultural business for purposes of the renewable energy
generating facility; and
6. Provides the electric utility with a certification,
attested under oath, as to the amount of land being used for renewable
generation.
"Time-of-use customer" means an agricultural net
metering customer or net metering customer receiving retail electricity supply
service under a demand charge-based time-of-use tariff.
"Time-of-use period" means an interval of time over
which the energy (kilowatt-hour) rate charged to a time-of-use customer does
not change.
"Time-of-use tier" or "tier" means all
time-of-use periods given the same name (e.g., on-peak, off-peak, critical
peak, etc.) for the purpose of time-differentiating energy
(kilowatt-hour)-based charges. The rates associated with a particular tier may
vary by day and by season.
20VAC5-315-30. Company notification.
A. A prospective agricultural net metering customer or a
prospective net metering customer (hereinafter referred to as
"customer") shall submit a completed commission-approved notification
form to the electric distribution company and, if different from the electric
distribution company, to the energy service provider, according to the time
limits in this subsection. If the prospective customer has contracted with
another person to own or operate, or both, the generator or generators, then
the notice will include detailed, current, and accurate contract information
for the owner or operator, or both, including without limitation, the name and
title of one or more individuals responsible for the interconnection and
operation of the generator or generators, a telephone number, a physical street
address other than a post office box, a fax number, and an email address for
each such person.
1. A residential customer shall notify its supplier and
receive approval to interconnect prior to installation or adding capacity to an
electrical generating facility. The electric distribution company shall have 30
days from the date of notification to determine whether the requirements
contained in 20VAC5-315-40 have been met. The date of notification shall be
considered to be the third day following the mailing of the notification form
by the prospective customer.
2. A nonresidential customer shall notify its supplier and
receive approval to interconnect prior to installation or adding capacity to an
electrical generating facility. The electric distribution company shall have 60
days from the date of notification to determine whether the requirements
contained in 20VAC5-315-40 have been met. The date of notification shall be
considered to be the third day following the mailing of the notification form
by the prospective customer.
B. Thirty-one days after the date of notification for a
residential customer, and 61 days after the date of notification for a
nonresidential customer, the prospective customer may interconnect and begin
operation of the generating facility unless the electric distribution company
or the energy service provider requests a waiver of this requirement under the
provisions of 20VAC5-315-80 prior to the 31st or 61st day, respectively. In
cases where the electric distribution company or energy service provider
requests a waiver, a copy of the request for waiver must be mailed
simultaneously by the requesting party to the prospective customer and to the commission's
Division of Energy Public Utility Regulation.
C. The electric distribution company shall file with the
commission's Division of Energy Public Utility Regulation a copy
of each completed notification form within 30 days of final interconnection.
20VAC5-315-40. Conditions of interconnection.
A. A prospective customer may begin operation of the
generating facility on an interconnected basis when:
1. The customer has properly notified both the electric
distribution company and energy service provider (in accordance with
20VAC5-315-30) of the customer's intent to interconnect.
2. If required by the electric distribution company's tariff,
the customer has installed a lockable, electric distribution company
accessible, load breaking manual disconnect switch at each of the facility's
generators.
3. The licensed electrician who installs the customer's
generator or generators certifies, by signing the commission-approved
notification form, that any required manual disconnect switch or switches are
being installed properly and that the generator or generators have been
installed in accordance with the manufacturer's specifications as well as all
applicable provisions of the National Electrical Code. If the customer or
licensed Virginia Class A or B general contractor installs the customer's
generator or generators, the signed final electrical inspection can be used in
lieu of the licensed electrician's certification.
4. The vendor certifies, by signing the commission-approved
notification form, that the generator or generators being installed are
in compliance with the requirements established by Underwriters Laboratories or
other national testing laboratories in accordance with IEEE Standard 1547,
Standard for Interconnecting Distributed Resources with Electric Power Systems,
July 2003.
5. In the case of static inverter-connected generators with an
alternating current capacity in excess of 10 kilowatts, the customer has had
the inverter settings inspected by the electric distribution company. The
electric distribution company may impose a fee on the customer of no more than
$50 for each generator that requires this inspection.
6. In the case of nonstatic inverter-connected generators, the
customer has interconnected according to the electric distribution company's
interconnection guidelines and the electric distribution company has inspected
all protective equipment settings. The electric distribution company may impose
a fee on the customer of no more than $50 for each generator that requires this
inspection.
7. The following requirements shall be met before
interconnection may occur:
a. Electric distribution facilities and customer impact
limitations. A customer's generator shall not be permitted to interconnect to
distribution facilities if the interconnection would reasonably lead to damage
to any of the electric distribution company's facilities or would reasonably
lead to voltage regulation or power quality problems at other customer revenue
meters due to the incremental effect of the generator on the performance of the
electric distribution system, unless the customer reimburses the electric
distribution company for its cost to accommodate the interconnection, including
the reasonable cost of equipment required for the interconnection.
b. Secondary, service, and service entrance limitations. The
capacity of the generators at any one service location shall be less than the
capacity of the electric distribution company-owned secondary, service, and
service entrance cable connected to the point of interconnection, unless the
customer reimburses the electric distribution company for the reasonable cost
of equipment required for the interconnection.
c. Transformer loading limitations. A customer's generator
shall not have the ability to overload the electric distribution company's
transformer, or any transformer winding, beyond manufacturer or nameplate
ratings, unless the customer reimburses the electric distribution company for
the reasonable cost of equipment required for the interconnection.
d. Integration with electric distribution company facilities
grounding. The grounding scheme of each generator shall comply with IEEE 1547,
Standard for Interconnecting Distributed Resources with Electric Power Systems,
July 2003, and shall be consistent with the grounding scheme used by the
electric distribution company. If requested by a prospective customer, the
electric distribution company shall assist the prospective customer in
selecting a grounding scheme that coordinates with its distribution system.
e. Balance limitation. The generator or generators shall not
create a voltage imbalance of more than 3.0% at any other customer's revenue
meter if the electric distribution company transformer, with the secondary
connected to the point of interconnection, is a three-phase transformer, unless
the customer reimburses the electric distribution company for the reasonable
cost of equipment required for the interconnection.
B. A prospective customer shall not be allowed to
interconnect a generator if doing so will cause the total rated generating
alternating current capacity of all interconnected net metered generators, as
defined in 20VAC5-315-20, within that customer's electric distribution
company's Virginia service territory to exceed 1.0% of that company's Virginia
peak-load forecast for the previous year. In any case where a prospective
customer has submitted a notification form required by 20VAC5-315-30 and that
customer's interconnection would cause the total rated generating alternating
current capacity of all interconnected net metered generators, as defined in
20VAC5-315-20, within that electric distribution company's service territory to
exceed 1.0% of that company's Virginia peak-load forecast for the previous
year, the electric distribution company shall, at the time it becomes aware of
the fact, send written notification to the prospective customer and to the
commission's Division of Energy Public Utility Regulation that
the interconnection is not allowed. In addition, upon request from any
customer, the electric distribution company shall provide to the customer the
amount of capacity still available for interconnection pursuant to § 56-594 D
of the Code of Virginia.
C. Neither the electric distribution company nor the energy
service provider shall impose any charges upon a customer for any
interconnection requirements specified by this chapter, except as provided
under subdivisions A 5, A 6, and A 7 of this section,
20VAC5-315-50, and 20VAC5-315-70 as related to additional metering.
D. A customer shall immediately notify the electric
distribution company of any changes in the ownership of, operational
responsibility for, or contact information for any of the customer's
generators.
20VAC5-315-75. Interconnection of small agricultural
generators.
Small agricultural generators electing to interconnect
pursuant to this section shall enter into a power purchase agreement with its
supplier to sell all of the electricity generated from its small agricultural
generating facility. The customer's supplier shall be obligated by the power
purchase agreement to purchase the excess generation at a price equal to a rate
agreed upon by the parties that is not less than the utility's
commission-approved avoided cost tariff for energy and capacity.
Small agricultural generators with renewable energy
certificates or other environmental attributes generated by the small
agricultural generating facility shall have the rights described in
20VAC5-315-50.
Small agricultural generators shall abide by the small
generator interconnection process described in 20VAC5-314. Such customer shall
be responsible for all costs associated with any interconnection or engineering
studies that may be required prior to interconnection.
DOCUMENTS INCORPORATED BY REFERENCE
1547, IEEE Standard for Interconnecting Distributed Resources
with Electric Power Systems, July 2003, The Institute of Electrical and
Electronics Engineers, Inc.
Rider G, Renewable Energy Program, Virginia Electric and
Power Company, January 1, 2009.
Rider
G, Renewable Energy Program, Virginia Electric and Power Company, January 1,
2012
VA.R. Doc. No. R18-5222; Filed August 25, 2017, 12:31 p.m.