TITLE 20. PUBLIC UTILITIES AND TELECOMMUNICATIONS
REGISTRAR'S NOTICE: The
State Corporation Commission is claiming an exemption from the Administrative
Process Act in accordance with § 2.2-4002 A 2 of the Code of Virginia,
which exempts courts, any agency of the Supreme Court, and any agency that by
the Constitution is expressly granted any of the powers of a court of record.
Title of Regulation: 20VAC5-335. Regulations
Governing the Deployment of Energy Storage (adding 20VAC5-335-10 through 20VAC5-335-130).
Statutory Authority: §§ 12.1-13 and 56-585.5 of the Code
of Virginia.
Public Hearing Information: A public hearing will be
held upon request.
Public Comment Deadline: November 2, 2020.
Agency Contact: Michael Cizenski, Principle Utilities
Engineer, Public Utilities Regulation, State Corporation Commission, P.O. Box
1197, Richmond, VA 23218, telephone (804) 371-9441 or email mike.cizenski@scc.virginia.gov.
Summary:
The proposed action establishes Regulations Governing the
Deployment of Energy Storage (20VAC5-335) to (i) set minimum interim targets
for Phase I and Phase II Utilities to conduct annual competitive procurement
for energy storage and (ii) require each Phase I or Phase II Utility to propose
behind-the-meter incentives, non-wires alternative programs, and peak demand
reduction programs related to energy storage. The proposed chapter also
establishes processes for the permitting of non-utility energy storage facilities
and licensing and registration of energy storage aggregators.
AT RICHMOND, SEPTEMBER 11, 2020
COMMONWEALTH OF VIRGINIA, ex rel.
STATE CORPORATION COMMISSION
CASE NO. PUR-2020-00120
Ex Parte: In the matter of establishing rules
and regulations pursuant to § 56-585.5 E 5
of the Code of Virginia related to the
deployment of energy storage
ORDER FOR NOTICE AND COMMENT
During its 2020 Session, the Virginia General Assembly
enacted the Virginia Clean Economy Act ("VCEA").1 Among
other things, the VCEA, in Code § 56-585.5 E, requires Appalachian Power
Company ("APCo") and Virginia Electric and Power Company
("Dominion") to petition the State Corporation Commission
("Commission") for approval to construct or acquire 400 megawatts
("MW") and 2,700 MW, respectively, of new utility-owned energy
storage resources by 2035. Section 56-585.5 E 5 further provides in part that:
By January 1, 2021, the Commission shall adopt regulations to
achieve the deployment of energy storage for the Commonwealth required in
subdivisions 1 and 2, including regulations that set interim targets and update
existing utility planning and procurement rules. The regulations shall include
programs and mechanisms to deploy energy storage, including competitive solicitations,
behind-the-meter incentives, non-wires alternatives programs, and peak demand
reduction programs.
On June 29, 2020, the Commission established this proceeding
for the purpose of complying with this statutory requirement and sought comment
on several questions raised by § 56-585.5 E 5 of the Code. The Commission
directed APCo and Dominion to submit comments and permitted any other
interested person or entity to submit comments. In addition to answering
specific questions, commenters were also permitted to propose specific
regulations.2
Comments were filed in this proceeding by: Dominion and APCo;
the Virginia Office of the Attorney General, Division of Consumer Counsel;
esVolta, LP; Delorean Power LLC ("Delorean"); the U.S. Energy Storage
Association ("ESA"); Able Grid Energy Services, Inc.; Virginia
Advanced Energy Economy ("AEE"); the Maryland-DC-Delaware-Virginia
Solar Energy Industries Association ("MDV SEIA") and the Solar Energy
Industries Association ("SEIA"); GRID Alternatives Mid-Atlantic; the
Virginia Department of Mines, Minerals and Energy; Highland Electric
Transportation, Inc.; the Virginia, Maryland and Delaware Association of
Electric Cooperatives; the Sierra Club; the Southern Environmental Law Center,
Appalachian Voices, the Virginia Conservation Network, the Chesapeake Climate
Action Network, the Virginia League of Conservation Voters, the Piedmont
Environmental Council, the Rappahannock League for Environmental Protection,
and the National Parks Conservation Association; the Institute for Policy
Integrity at New York University School of Law; LS Power Development LLC
("LS Power"); the Virginia Oil and Gas Association
("VOGA"); Solar United Neighbors; and an individual.3
Proposed regulations were filed by APCo and Dominion; ESA;
and Delorean.4
NOW THE COMMISSION, upon consideration of the foregoing, is
of the opinion and finds as follows. Based on comments and draft regulations
filed in this proceeding, the Commission's Staff ("Staff") has
prepared Proposed Rules which are appended to this Order. We will direct that
notice of the Proposed Rules be given to the public and that interested persons
be provided an opportunity to file written comments on, propose modifications
or supplements to, or request a hearing on the Proposed Rules. We further find
that a copy of the Proposed Rules should be sent to the Registrar of
Regulations for publication in the Virginia Register of Regulations.
The Commission takes judicial notice of the ongoing public
health emergency related to the spread of the coronavirus, or COVID-19, and the
declarations of emergency issued at both the state and federal levels.5
The Commission has taken certain actions, and may take additional actions going
forward, which could impact the procedures in this proceeding.6
Consistent with these actions, in regard to the terms of the procedural
framework established below, the Commission will, among other things, direct
the electronic filing of comments.
Accordingly, IT IS ORDERED THAT:
(1) All filings in this matter should be submitted
electronically to the extent authorized by Rule 5 VAC 5-20-150, Copies and
Format, of the Commission's Rules of Practice and Procedure ("Rules of
Practice").7 For the duration of the COVID-19 emergency, any
person seeking to hand deliver and physically file or submit any pleading or
other document shall contact the Clerk's Office Document Control Center at
(804) 371-9838 to arrange the delivery.8
(2) The Commission's Division of Information Resources shall
forward a copy of this Order for Notice and Comment ("Order"),
including a copy of the Proposed Rules, to the Registrar of Regulations for
publication in the Virginia Register of Regulations.
(3) An electronic copy of the Proposed Rules may be obtained
by submitting a request to Michael Cizenski in the Commission's Division of
Public Utility Regulation at the following email address: Mike.Cizenski@scc.virginia.gov.
An electronic copy of the Proposed Rules can be found at the Division of Public
Utility Regulation's website: https://scc.virginia.gov/pages/Rulemaking. Interested persons
may also download unofficial copies of the Order and the Proposed Rules from
the Commission's website: https://scc.virginia.gov/pages/Case-Information.
(4) The Commission's Division of Public Utility Regulation
shall provide copies of this Order by electronic transmission, or when
electronic transmission is not possible, by mail, to: individuals,
organizations, and companies who have been identified by the Staff as
interested in the development of energy storage in the Commonwealth, including
those entities and individuals previously filing comments in this proceeding.
(5) On or before November 2, 2020, any interested person may
file comments on the Proposed Rules by following the instructions found on the
Commission's website: https://scc.virginia.gov/casecomments/Submit-Public-Comments.
Such comments may also include proposals and hearing requests. All comments
shall refer to Case No. PUR-2020-00120. Any request for hearing shall state
with specificity why the issues raised in the request for hearing cannot be
adequately addressed in written comments. If a sufficient request for hearing
is not received, the Commission may consider the matter and enter an order
based upon the papers filed herein.
(6) On or before November 16, 2020, the Staff shall file with
the Clerk of the Commission a report on or a response to any comments,
proposals, or requests for hearing submitted to the Commission on the Proposed
Rules.
(7) This matter is continued.
A COPY hereof shall be sent electronically by the Clerk of
the Commission to all persons on the official Service List in this matter. The
Service List is available from the Clerk of the Commission.
_______________________________
1Senate Bill 851, 2020 Va. Acts ch. 1194, and identical
House Bill 1526, 2020 Va. Acts ch. 1193 (effective July 1, 2020).
2On July 20, 2020, Dominion and APCo filed a Motion for
Limited Extension of Time to File Proposed Regulations and for Expedited
Consideration requesting an extension of the deadline to propose specific
regulations implementing Code § 56-585.5 E 5 from July 29, 2020 to August 14,
2020. The Commission subsequently granted the motion and extended the deadline
for the filing of proposed regulations in this proceeding to August 14, 2020.
3LS Power, VOGA and Solar United Neighbors filed
comments after the deadline for submission; the Commission exercises its
discretion herein to accept those comments out of time.
4MDV SEIA, SEIA, and AEE filed joint comments supportive
of the draft regulations filed by ESA.
5See, e.g., Executive Order No. 51, Declaration of a
State of Emergency Due to Novel Coronavirus, COVID-19, issued March 12, 2020,
by Gov. Ralph S. Northam. See also Executive Order No. 53, Temporary
Restrictions on Restaurants, Recreational, Entertainment, Gatherings,
Non-Essential Retail Businesses, and Closure of K-12 Schools Due to Novel
Coronavirus (COVID-19), issued March 23, 2020, by Governor Ralph S. Northam, and
Executive Order No. 55, Temporary Stay At Home Order Due to Novel Coronavirus
(COVID-19), issued March 30, 2020, by Governor Ralph S.
Northam. These and subsequent Executive Orders related to COVID-19 may be
found at: https://www.governor.virginia.gov/executive-actions/.
6See, e.g., Commonwealth of Virginia, ex rel. State
Corporation Commission, Ex Parte: Electronic Service of Commission Orders, Case
No. CLK-2020-00004, Doc. Con. Cen. No. 200330035, Order Concerning Electronic
Service of Commission Orders (Mar. 19, 2020), extended by Doc. Con. Cen. No.
200520105, Order Regarding the State Corporation Commission's Revised Operating
Procedures During COVID-19 Emergency (May 11, 2020); Commonwealth of Virginia,
ex rel., State Corporation Commission, Ex Parte: Revised Operating Procedures
During COVID-19 Emergency, Case No. CLK-2020-00005, Doc. Con. Cen. No.
200330042, Order Regarding the State Corporation Commission's Revised Operating
Procedures During COVID-19 Emergency (Mar. 19, 2020) ("Revised Operating
Procedures Order"), extended by Doc. Con. Cen. No. 200520105, Order
Regarding the State Corporation Commission's Revised Operating Procedures
During COVID-19 Emergency (May 11, 2020); Commonwealth of Virginia, ex rel.
State Corporation Commission, Ex Parte: Electronic service among parties during
COVID-19 emergency, Case No. CLK-2020-00007, Doc. Con. Cen. No. 200410009,
Order Requiring Electronic Service (Apr. 1, 2020).
75 VAC 5-20-10 et seq.
8As noted in the Commission's Revised Operating
Procedures Order, submissions to the Commission's Clerk's Office via U.S. mail
or commercial mail equivalents may not be processed for an indefinite period
due to the COVID-19 emergency.
CHAPTER 335
REGULATIONS GOVERNING THE DEPLOYMENT OF ENERGY STORAGE
20VAC5-335-10. Purpose and applicability.
This chapter is promulgated pursuant to § 56-585.5 E 5 of
the Code of Virginia to achieve the deployment of energy storage for the
Commonwealth. Each Phase I or Phase II Utility is subject to 20VAC5-335-30
through 20VAC5-335-70, 20VAC5-335-120, and 20VAC5-335-130.
Non-utility developers, owners, operators, and aggregators of energy storage
are subject to 20VAC5-335-80 through 20VAC5-335-130.
Electric cooperatives are not subject to this chapter.
20VAC5-335-20. Definitions.
The following words and terms when used in this chapter
shall have the following meanings unless the context clearly indicates
otherwise:
"Behind the meter" means any system that is on
the customer side of the utility service meter.
"Behind-the-meter incentive" means any incentive
that encourages an end-use electric customer to implement energy storage
systems that are connected to the customer side of the utility service meter,
regardless of who actually owns the energy storage equipment.
"Commission" means the Virginia State
Corporation Commission.
"Demand-side management program" means energy
efficiency, demand response, or peak shaving programs approved by the
commission that a utility may offer to customers pursuant to § 56-585.1 A 5 of
the Code of Virginia.
"Energy storage" means any technology that is
capable of absorbing energy, storing that energy for a period of time, and
re-delivering that energy after storage.
"Energy storage aggregator" means a person or
entity that, as an agent or intermediary, (i) offers to purchase or purchases
energy storage system capabilities; or (ii) offers to arrange for or arranges
for the purchase of energy storage system capabilities for the purposes of
combining or aggregating those capabilities to enable the participation of
multiple energy storage systems in electricity markets where such individual
systems could not participate individually.
"Energy storage capacity" means the maximum
amount of stored energy of the energy storage system in kilowatt-hours or
megawatt-hours that can be delivered to the grid.
"Energy storage facility" or "energy
storage system" means an energy storage resource and any equipment, other
than a transmission or distribution line, needed to interconnect the energy
storage resource to the utility's electric system. This additional equipment
can include switchgear, transformers, inverters, switches, cables, wires,
conductors, bus work, protection devices and systems, communication and control
devices and systems, fire protection systems, and environmental protection
systems.
"Energy storage power rating" means the total
possible instantaneous discharge capability in kilowatts or megawatts of the
energy storage system, or the maximum sustained rate of discharge that the
energy storage system can achieve starting from a fully charged state to a
fully discharged state.
"Energy storage project" means an energy storage
facility with a specified location and an associated nameplate capacity.
"Energy storage resource" means (i) a resource
capable of collecting energy from the electric power grid or a power generation
facility and then discharging the energy at a future point in time to provide
electricity or other grid services, or (ii) a resource capable of the active or
dynamic exchange of energy.
"Non-wires alternative" means any electricity
grid investment, project, or program that uses nontraditional transmission or
distribution solutions, such as distributed generation, energy storage, energy
efficiency, demand response, and grid software and controls, to delay or remove
the need for traditional system upgrades of equipment, such as transmission or
distribution lines or transformers, without impacting the safety or overall
performance of the electric power system.
"Peak demand reduction program" means any
project or program aimed at shifting time of use of electricity from one period
to another for the overall economic and reliability benefit of the electric
power grid.
"Person" means any individual, corporation,
partnership, association, company, business, trust, joint venture, or other
private legal entity, and the Commonwealth or any municipality.
"Phase I Utility" has the same meaning as
provided in subdivision A 1 of § 56-585.1 of the Code of Virginia.
"Phase II Utility" has the same meaning as
provided in subdivision A 1 of § 56-585.1 of the Code of Virginia.
"Storage duration" means the amount of time an
energy storage system can discharge at its energy storage power rating before
depleting the stored usable energy when the system is at maximum energy
capacity.
20VAC5-335-30. Minimum interim targets for energy storage
deployment by Phase I and Phase II Utilities.
A. A Phase I Utility shall petition the commission for any
necessary approvals to construct or acquire the level of energy storage
capacity by the following dates:
1. By December 31, 2025, 25 megawatts;
2. By December 31, 2030, an additional 125 megawatts for a
total of 150 megawatts; and
3. By December 31, 2035, an additional 250 megawatts for a
total of 400 megawatts.
B. A Phase II Utility shall petition the commission for
any necessary approvals to construct or acquire the level of energy storage
capacity by the following dates:
1. By December 31, 2025, 250 megawatts;
2. By December 31, 2030, an additional 950 megawatts for a
total of 1,200 megawatts; and
3. By December 31, 2035, an additional 1,500 megawatts for
a total of 2,700 megawatts.
C. At least 35% of energy storage facilities placed into
service by a Phase I or Phase II Utility shall be (i) purchased by the Phase I
or Phase II Utility from a party other than the utility, or (ii) owned by a
party other than the Phase I or Phase II Utility with the capacity from such
facilities sold to the utility. The 35% threshold shall also apply to each
interim targets period identified in this section and a Phase I or Phase II
Utility's acquisition of energy storage facilities, and purchases of capacity
from its own utility-affiliated interests shall not count toward this 35% threshold.
D. Any type of energy storage technology shall count
toward the interim targets set forth in subsections A and B of this section.
E. Each Phase I or Phase II Utility shall report on its
plan to meet these interim targets and its progress toward meeting these
interim targets in the proceedings established by § 56-585.5 D 4 and §§ 56-597
through 56-599 of the Code of Virginia, consistent with the requirements of
each respective statute.
20VAC5-335-40. Procurement of energy storage projects by
Phase I and Phase II Utilities.
A. In procuring energy storage projects, each Phase I or
Phase II Utility shall use competitive bidding to the extent practicable,
consistent with § 56-233.1 of the Code of Virginia.
B. Beginning in 2021 and ending in 2035 or when the storage
targets are met, whichever is sooner, each Phase I or Phase II Utility shall
sponsor at least one competitive solicitation for energy storage projects per
calendar year, consistent with the following requirements:
1. The request for proposals shall quantify and describe
the utility's need for energy or capacity.
2. The request for proposals shall be publicly announced
and made available for public review on the utility's website at least 45
calendar days prior to the closing of such request for proposals.
3. The request for proposals shall provide, at a minimum,
the following information: (i) the size, type, and timing of energy storage
resources for which the utility anticipates contracting; (ii) any minimum
thresholds that must be met by respondents; (iii) major assumptions to be used
by the utility in the bid evaluation process, including environmental emission
standards; (iv) detailed instructions for preparing bids so that bids can be
evaluated on a consistent basis; (v) the preferred general location of
additional energy storage capacity; and (vi) specific information concerning
the factors involved in determining the price and non-price criteria used for
selecting winning bids.
4. A utility may evaluate responses to the request for
proposals based on any criteria that it deems reasonable but shall at a minimum
consider the following in its selection process: (i) the status of a particular
project's development; (ii) the age of existing facilities; (iii) the
demonstrated financial viability of a project and the developer; (iv) a
developer's prior experience in the field; (v) the location and effect on the
transmission grid of an energy storage facility; (vi) the benefits to the
Commonwealth that are associated with particular projects, including regional
economic development and the use of goods and services from Virginia
businesses; (vii) the environmental impacts of particular resources, including
impacts on air quality within the Commonwealth and the carbon intensity of the
utility's generation portfolio; and (viii) how any project impacts the goals
established by the Virginia Environmental Justice Act (§ 2.2-234 et seq. of the
Code of Virginia).
5. A utility shall maintain documentation of its reasoning
for rejecting any specific response.
C. Each utility shall report on any competitive
solicitations for energy storage resources as part of the annual plan required
by § 56-585.5 D 4 of the Code of Virginia.
20VAC5-335-50. Behind-the-meter incentives by Phase I and
Phase II Utilities.
As part of the annual proceeding required by § 56-585.5 D
4 of the Code of Virginia, each Phase I or Phase II Utility shall address
behind-the-meter incentives related to energy storage. Each Phase I or Phase II
Utility shall file with the commission applications for approval of
behind-the-meter incentives related to energy storage. If the utility proposes
to offer any such behind-the-meter incentives to customers through a
demand-side management program, the utility may seek approval through any
existing processes for demand-side management programs under § 56-585.1 A 5 of
the Code of Virginia, rather than through a separate proceeding under this
section.
20VAC5-335-60. Non-wires alternative programs by Phase I and
Phase II Utilities.
As part of the annual proceeding required by § 56-585.5 D
4 of the Code of Virginia, each Phase I or Phase II Utility shall address
non-wires alternative programs related to energy storage. Each Phase I or Phase
II Utility shall file with the commission applications for approval of non-wires
alternative programs related to energy storage. If the utility proposes to
offer non-wires alternative programs to customers through a demand-side
management program, the utility may seek approval through any existing
processes for demand-side management programs under § 56-585.1 A 5 of the Code
of Virginia, rather than through a separate proceeding under this section.
20VAC5-335-70. Peak demand reduction programs by Phase I and
Phase II Utilities.
As part of the annual proceeding required by § 56-585.5 D
4 of the Code of Virginia, each Phase I or Phase II Utility shall address peak
demand reduction programs related to energy storage. Each Phase I or Phase II
Utility shall file with the commission applications for approval of peak demand
reduction programs related to energy storage. If the utility proposes to offer
any such peak demand reduction programs to customers through a demand-side
management program, the utility may seek approval through any existing
processes for demand-side management programs under § 56-585.1 A 5 of the Code
of Virginia, rather than through a separate proceeding under this section.
20VAC5-335-80. Permitting of non-utility energy storage
facilities.
A. Other than a Phase I or Phase II Utility, each person
seeking to construct and operate an energy storage facility in the Commonwealth
with an energy storage power rating of 100 kilowatts or greater, either on a
stand-alone basis or on an aggregated basis facilitated by an energy storage
aggregator, shall either (i) obtain a permit from the commission pursuant to
this section, or (ii) apply for and receive a certificate of public convenience
and necessity from the commission pursuant to § 56-580 of the Code of Virginia
for the energy storage facility, prior to commencing construction or operation.
If such person applies for and receives a certificate of public convenience and
necessity from the commission, a permit shall not be required.
B. In evaluating a permit application, the commission
shall make a determination for approval based upon a finding that the energy
storage facility (i) will have no material adverse effect upon reliability of
electric service provided by any regulated public utility; (ii) does not
adversely impact any goal established by the Virginia Environmental Justice Act
(§ 2.2-234 et seq. of the Code of Virginia); and (iii) is not otherwise
contrary to the public interest.
C. Other than a Phase I or Phase II Utility, each person
applying for a permit to construct and operate an energy storage facility with
an energy storage power rating of 100 kilowatts or greater shall file an
application with the clerk of the commission. If the applicant becomes aware of
any material changes to any information while the application is pending, the
applicant shall inform the commission of such changes within 10 calendar days.
Applications shall include the following information:
1. Legal name of the applicant as well as any trade name.
2. A description of the applicant's authorized business
structure, identifying the state authorizing such structure and the associated
date (e.g., if incorporated, the state and date of incorporation; if a limited
liability company, the state issuing the certificate of organization and the
date of issuance).
3. Name and business addresses of all principal corporate
officers and directors, partners, and LLC members, as appropriate.
4. Financial information for the applicant or principal
participant in the project. If the applicant or principal participant is a
private entity, financial information should include an analysis of the
entity's financial condition and audited financial statements for the two most
recent fiscal years. If the applicant or principal participant is a public
company, financial information should include a copy or a link to where a copy
can be found on the internet of the entity's most recent stockholder report and
most recent Securities and Exchange Commission Form 10 K. If such information
is unavailable, provide evidence that applicant has the financial resources or
access to capital necessary to complete the proposed project.
5. A discussion of the applicant's qualifications,
including:
a. A summary of other projects developed and managed by the
applicant. Include location, status, and operational history.
b. A description of any affiliation with an incumbent
electric utility as defined in § 56-576 of the Code of Virginia.
c. A disclosure of any affiliate relationship with any
other permit holder.
6. Specific information about the site for the proposed
facility, including:
a. A written description of the location, including
identification of the city or county in which the facility will be constructed.
Such description should be suitable for newspaper publication and sufficiently
identify any affected areas.
b. A description of the site and a topographical map
depiction of the proposed site.
c. The status of site acquisition (e.g., purchase option,
ownership).
d. A description of any applicable local zoning or land use
approvals required and the status of such approvals.
7. Specific information about the proposed facility,
including:
a. Description of all major systems, including energy
storage technology type and battery storage chemistry type, if applicable;
intended uses; intended facility useful life; facility configuration; and
expected suppliers of major components.
b. Energy storage power rating, energy capacity, and
storage duration.
c. Estimated costs and schedule for construction, testing,
and commercialization.
d. Site layouts that provide for integration of energy
storage systems with adequate spacing and property setback requirements
incorporated.
e. Codes and standards to which the proposed facility will
be constructed.
f. Where applicable, the manner and location of the
facility's interconnection to the transmission or distribution grid.
8. A general discussion of the selection process for the
energy storage technology, including a description of any competitive
procurement processes used.
9. A general discussion of economic development impacts of
the project.
10. A list of other local, state, or federal government
agencies whose requirements must be met in connection with the construction or
operation of the project and a statement of the status of the approval
procedures for each of these agencies.
11. An analysis of the environmental impact of the project.
This analysis shall include the impacts on the environment and natural
resources, analysis of alternatives considered, unavoidable adverse impacts,
mitigation measures proposed to minimize unavoidable impacts, and any
irreversible environmental changes. The information required by this
subdivision shall be submitted to the Department of Environmental Quality,
simultaneously with its filing with the commission, for coordination and review
by state agencies responsible for environmental and natural resource
protection. The information shall identify:
a. Required air permits, expected restrictions, expected
emissions, rates of emissions, and any needed emissions offsets or allowances.
b. Required permits for water withdrawals, expected
restrictions, the amount of water estimated to be used, the source of such
water, identification of a backup source of water, if any, and identification
of any facilities that need to be constructed to provide such water.
c. Required permits for water discharge and potential
impacts on regional water flows.
d. Required permits related to the wetlands and an
identification of any tidal and nontidal wetlands located near the proposed
site and how such wetlands will be impacted by applicant's proposed facility.
e. Impact of solid and hazardous wastes on local water
resources.
f. Impact on natural heritage resources and on threatened
and endangered species.
g. Erosion and sediment control measures.
h. Archaeological, historic, scenic, cultural, or
architectural resources in the area.
i. Chesapeake Bay Preservation Areas designated by the
locality.
j. Wildlife resources.
k. Agricultural and forest resources and federal, local,
state, or private parks and recreation areas.
l. Use of pesticides and herbicides.
m. Geology and mineral resources, caves, and sinkholes.
n. Transportation infrastructure.
12. An analysis of the social impact of the project,
including a general discussion of why the facility will not have a
disproportionate adverse impact on "historically economically
disadvantaged communities" as defined in § 56-576 of the Code of
Virginia.
13. A general discussion of how the project will promote
environmental justice in environmental justice communities and fenceline
communities consistent with the Virginia Environmental Justice Act (§ 2.2-234
et seq. of the Code of Virginia).
14. A general discussion of reliability impacts, including:
a. A description of interconnection requirements and needed
interconnection facilities. Any such facilities shall be depicted on a
topographic map.
b. A description of the potential impact of the proposed
facility on the interconnected system. Discussion should identify and summarize
any system impact studies or proposed studies.
c. A description of anticipated services that may be
provided to any transmission service provider or local distribution company,
including associated costs and benefits.
d. A discussion of existing and expected generation
reserves in the region and the impact of the proposed facility on such
reserves.
15. A discussion of safety measures the applicant will
implement, including fire and explosion protection, detection and mitigation
measures, and an emergency response plan, as well as a discussion of whether
such measures are compliant with all applicable codes and standards.
16. A discussion of the projected useful life of the energy
storage facility, including known or projected performance degradation,
roundtrip efficiency, and the proposed plan for and cost of decommissioning at
the end of the facility's useful life.
17. A discussion of whether the proposed facility is not
contrary to the public interest. The discussion shall include an analysis of
any reasonably known impacts the proposed facility may have upon reliability of
service to and rates paid by customers of any regulated public utility
providing electric service in the Commonwealth.
Any application that fails to conform to the requirements
shall be incomplete. No action shall be taken on any application until deemed
complete and filed.
Upon receipt of a complete permit application pursuant to
this section, the commission shall enter an order providing notice to
appropriate persons and an opportunity to comment on the application. The
commission shall issue a permit for construction and operation of the energy
storage facility upon finding the applicant satisfies the requirements
established by this section.
D. Construction and operation of an energy storage
facility in the Commonwealth with an energy storage power rating of less than
100 kilowatts may be undertaken without complying with the filing requirements
established by this section. Persons desiring to construct and operate such
facilities shall (i) submit a letter stating the location, size, and technology
of the energy storage facility to (a) the Director of the commission's Division
of Public Utility Regulation and (b) the utility in whose certificated service
territory the energy storage facility is located; and (ii) comply with all
other requirements of federal, state, and local law.
E. In addition to the requirements of this section, each
person seeking to operate an energy storage facility must complete either the
interconnection process required by the commission's Regulations Governing
Interconnection of Small Electrical Generators and Storage (20VAC5-314) or any
federally approved process established by the regional transmission
organization.
F. Within 30 days of any transfer or assignment of an
energy storage facility for which a permit was granted by the commission, the
permit holder shall notify the commission and the utility in whose certificated
service territory the energy storage facility is located of such transfer or
assignment. The notice shall include (i) the date of transfer or assignment;
(ii) the information required in subdivisions C 1 through C 5 of this section
for the new permit holder; and (iii) a declaration by the new permit holder
that it agrees to abide by all initial and continuing requirements of the
permit.
G. Any person receiving a permit to operate an energy
storage facility in the Commonwealth pursuant to this section shall comply with
all initial and continuing requirements of the commission's permitting process.
Should the commission determine, upon complaint of any interested person or the
Attorney General or upon staff motion or its own motion that a permitted
operator of an energy storage facility has failed to comply with any of the
requirements of this section or a commission order, the commission may, after
providing due notice and an opportunity for a hearing, suspend or revoke the
permit or take any other actions permitted by law or regulations as it may deem
necessary to protect the public interest.
20VAC5-335-90. Licensing of energy storage aggregators.
A. Other than a Phase I or Phase II Utility, each person
seeking to conduct business as an energy storage aggregator shall obtain a
license from the commission prior to commencing operations.
B. Each person applying for a license to conduct business
as an energy storage aggregator shall file an application with the clerk of the
commission. If the applicant becomes aware of any material changes to any
information while the application is pending, the applicant shall inform the
commission of such changes within 10 calendar days. Applications shall include
the following information:
1. Legal name of the applicant as well as any trade name.
2. A description of the applicant's authorized business
structure, identifying the state authorizing such structure and the associated
date (e.g., if incorporated, the state and date of incorporation; if a limited
liability company, the state issuing the certificate of organization and the
date of issuance).
3. Name and business addresses of all principal corporate
officers and directors, partners, and limited liability corporation (LLC)
members, as appropriate.
4. Physical business addresses and telephone numbers of the
applicant's principal office and any Virginia office location.
5. Whether the applicant is an affiliate of a Phase I or
Phase II Utility. If so, the application shall further provide a description of
internal controls the applicant has designed to ensure that it and its
employees, contractors, and agents that are engaged in the (i) merchant,
operations, transmission, or reliability functions of the electric generation
systems, or (ii) customer service, sales, marketing, metering, accounting, or
billing functions do not receive information from the utility or from entities
that provide similar functions for or on behalf of the utility as would give
the affiliated energy storage aggregator an undue advantage over nonaffiliated
energy storage aggregators.
6. A list of states in which the applicant or an affiliate
conducts business as an energy storage aggregator, the names under which such
business is conducted, and a description of the businesses conducted.
7. Toll-free telephone number of the applicant's customer
service department.
8. Name, title, address, telephone number, and email
address of the applicant's liaison with the commission.
9. Name, title, and address of the applicant's registered
agent in Virginia for service of process.
10. If a foreign corporation, a copy of the applicant's
authorization to conduct business in Virginia from the commission or if a
domestic corporation, a copy of the certificate of incorporation from the
commission.
11. Sufficient information to demonstrate, for purposes of
licensure with the commission, financial fitness commensurate with the services
proposed to be provided. Applicant shall submit the following information
related to general financial fitness:
a. If available, applicant's audited balance sheet and
income statement for the most recent fiscal year and published financial
information, such as the most recent Securities and Exchange Commission forms
10-K and 10-Q. If not available, other financial information for the applicant
or any other entity that provides financial resources to the applicant.
b. If available, proof of a minimum bond rating (or other
senior debt) of "BBB-" or an equivalent rating by a major rating
agency or a guarantee with a guarantor possessing a credit rating of
"BBB-" or higher from a major rating agency. If not available, other
evidence that will demonstrate the applicant's financial responsibility.
12. The name of the utility certificated to provide service
in the area in which the applicant proposes to provide service, the type of
services the applicant proposes to provide, and the class of customers to which
the applicant proposes to provide such services.
13. The following information related to the applicant's
fitness to operate as an energy storage aggregator:
a. Disclosure of any (i) civil, criminal, or regulatory
sanctions or penalties imposed or in place within the previous five years
against the company, any of its affiliates, or any officer, director, partner,
or member of an LLC or any of its affiliates pursuant to any state or federal
law or regulation; and (ii) felony convictions within the previous five years
that relate to the business of the company or to an affiliate of any officer,
director, partner, or member of an LLC.
b. Disclosure of whether any application for license or
authority to conduct the same type of business as it proposes to offer in
Virginia has ever been denied, whether any license or authority issued to it or
an affiliate has ever been suspended or revoked, and whether other sanctions
have been imposed.
c. If the applicant has
engaged in the provision of energy storage aggregation in Virginia or any other
state, a report of all instances of violations of reliability standards that
were determined to be the fault of the applicant, including unplanned outages,
failure to meet service obligations, and any other deviations from reliability
standards during the previous three years. The report shall include, for each
instance, the following information: (i) a description of the event; (ii) its
duration; (iii) its cause; (iv) the number of customers affected; (v) any
reports, findings, or issuances by regulators or electric and natural gas
system reliability organizations relating to the instance; (vi) any penalties
imposed; and (vii) whether and how the problem has been remedied.
14. A $250 registration fee payable to the commission.
15. A discussion of the proposed uses of the aggregated
resources, including the nature of the intended participation in wholesale
electric markets, if any.
16. Sufficient information to demonstrate technical fitness
commensurate with the service to be provided, to include:
a. The applicant's experience.
b. Identity of applicant's officers and key managers with
direct responsibility for the business operations conducted in Virginia and
their experience in the provision of storage aggregation.
c. Documentation of the applicant's membership or
participation in regional reliability councils or regional transmission
organizations, if any.
d. Billing service options the applicant intends to offer
and a description of the applicant's billing capability, including a
description of any related experience.
17. A copy of the applicant's dispute resolution procedure.
18. The standards of conduct to which the applicant adheres
or agrees to adhere to.
An officer with appropriate authority, under penalty of
perjury, shall attest that all information supplied on the application for
licensure form is true and correct and that, if licensed, the applicant will
abide by all applicable regulations of the commission.
C. Any application that fails to conform to the
requirements of this section shall be regarded as incomplete. No action shall
be taken on any application until deemed complete and filed.
D. Upon receipt of an application for a license to conduct
business as an energy storage aggregator, the commission shall enter an order
providing notice to appropriate persons and an opportunity for comments on the
application. The commission shall issue a license to conduct business as an
energy storage aggregator upon finding the applicant satisfies the requirements
established by this section.
E. A license to conduct business as an energy storage
aggregator granted under this section is valid until revoked or suspended by
the commission after providing due notice and an opportunity for a hearing or
until the energy storage aggregators abandons its license.
F. An energy storage
aggregator shall comply with all initial and continuing requirements of the
commission's licensure process and any reasonable registration processes
required by the utility in whose certificated service territory the energy
storage aggregator intends to operate. Should the commission determine, upon
complaint of any interested person or the Attorney General or upon staff motion
or its own motion that an energy storage aggregators has failed to comply with
any of the requirements of this section or a commission order, the commission
may, after providing due notice and an opportunity for a hearing, suspend or
revoke the energy storage aggregator's license or take any other actions
permitted by law or regulations as it may deem necessary to protect the public
interest.
20VAC5-335-100. Energy storage aggregator registration with
utility.
A. An energy storage aggregator shall submit to the
utility in whose certificated service territory it intends to operate proof of
licensure from the commission to provide energy storage aggregation services in
the Commonwealth. An energy storage aggregator shall provide notice of any
suspension or revocation of its license to the utility upon issuance of the
suspension or revocation by the commission.
B. An energy storage aggregator and the utility shall
exchange the names, telephone numbers, and email addresses of appropriate
internal points of contact to address operational and business coordination
issues and the names and addresses of their registered agents in Virginia.
20VAC5-335-110. Marketing by energy storage aggregators.
A. An energy storage aggregator shall provide accurate,
understandable information in any advertisements, solicitations, marketing
materials, or customer service contracts in a manner that is not misleading.
Marketing material found misleading by the commission will be withdrawn.
B. Customer service contracts shall include:
1. Explanations of the price for the energy storage
aggregator's services or, if the exact price cannot feasibly be specified, an
explanation of how the price will be calculated;
2. Explanations of how the customer will be compensated for
the value of their energy storage;
3. Length of the service contract, including any provisions
for automatic contract renewal;
4. Provisions for termination by the customer and by the
energy storage aggregator;
5. A statement of any minimum contract terms, minimum or
maximum storage requirements, minimum or fixed charges, and any other charges;
6. Applicable fees including start-up fees, cancellation
fees, late payment fees, and fees for checks returned for insufficient funds;
7. A notice of any billing terms and conditions;
8. A toll-free telephone number and an address for
inquiries and complaints;
9. In a conspicuous place, confirmation of the customer's
request for enrollment and the approximate date the customer's service shall
commence;
10. A notice that, upon request by the customer, the energy
storage aggregator shall provide a copy of its dispute resolution procedure;
and
11. A notice that, upon any change in the terms and
conditions of the contract, including any provisions governing price or pricing
methodology or assignment of the contract to another energy storage aggregator,
the energy storage aggregator shall communicate such changes to the customer at
least 30 days in advance of implementing such changes.
20VAC5-335-120. Confidentiality.
Where any application filed under this chapter, including
any supporting documents or pre-filed testimony, contains information that the
applicant asserts is confidential, the filing may be made under seal and
accompanied by a motion for a protective order or other confidential treatment
in accordance with 5VAC5-20-170.
20VAC5-335-130. Waiver.
A. Any request for a waiver of any provision in this
chapter may be granted upon such terms and conditions as the commission may
impose.
B. For good cause shown, any Phase I or Phase II Utility
may request a waiver of the commission's Rules Governing Utility Promotional
Allowances (20VAC5-313) for any proposed programs or incentives related to
energy storage set forth in 20VAC5-335-50, 20VAC335-60, and 20VAC5-335-70.
C. For good cause shown, any Phase I or Phase II Utility
may request a waiver of the commission's Regulations Governing the Functional
Separation of Incumbent Electric Utilities under the Virginia Electric Utility
Restructuring Act (20VAC5-202).
VA.R. Doc. No. R21-6401; Filed September 12, 2020, 5:10 p.m.